Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

CIMAPRA19-E02-1 Exam - Topic 7 Question 26 Discussion

An experienced IT project manager provides the following advice about planning a new project:"The project should start withaRequirements Analysis which should take 10 days. When this is finished Detailed Design (10 days) and Interface studies (15 days) can start at the same time. As soon as they are both complete Prototyping can start (30 days).Prototyping is the predecessor of both Implementation (10 days) and Data Conversion (20 days).Go-Live is the final activity (5 days) and follows when Implementation and Data Conversion are both complete."Using critical path analysis which statements are correct.Select ALL that apply.
A) The planned duration of the project is 80 days. and B) The critical path runs through five activities.
C) Data Conversion is non-critical and has float of 25 days.
D) There are four non-critical activities.

CIMAPRA19-E02-1 Exam - Topic 7 Question 26 Discussion

Actual exam question for CIMA's CIMAPRA19-E02-1 exam
Question #: 26
Topic #: 7
[All CIMAPRA19-E02-1 Questions]

An experienced IT project manager provides the following advice about planning a new project:

"The project should start withaRequirements Analysis which should take 10 days. When this is finished Detailed Design (10 days) and Interface studies (15 days) can start at the same time. As soon as they are both complete Prototyping can start (30 days).

Prototyping is the predecessor of both Implementation (10 days) and Data Conversion (20 days).

Go-Live is the final activity (5 days) and follows when Implementation and Data Conversion are both complete."

Using critical path analysis which statements are correct.

Select ALL that apply.

Show Suggested Answer Hide Answer
Suggested Answer: A, B

Contribute your Thoughts:

0/2000 characters
Yuriko
10 months ago
The critical path might not run through five activities, though.
upvoted 0 times
...
Jacqueline
10 months ago
I think there are definitely four non-critical activities.
upvoted 0 times
...
Gaston
11 months ago
Wait, how can Data Conversion have 25 days of float? Seems off.
upvoted 0 times
...
Aleshia
11 months ago
I agree, that adds up correctly!
upvoted 0 times
...
Francene
11 months ago
The total project duration is actually 80 days.
upvoted 0 times
...
Stevie
11 months ago
This looks like a straightforward question about the functionality of a hard disk in HP LaserJet printers. I'll start by quickly reviewing the options and see if any stand out as the clear answer.
upvoted 0 times
...
Stephen
11 months ago
I remember a practice question about blending modes—maybe it's similar to how we composite layers together?
upvoted 0 times
...
Shelba
11 months ago
Ah, yes, Selenium IDE is the tool for capture/playback. I remember that from our discussions in the review session. I'll go with option A.
upvoted 0 times
...

Save Cancel