Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

CIMA Exam CIMAPRA19-E02-1 Topic 7 Question 26 Discussion

Actual exam question for CIMA's CIMAPRA19-E02-1 exam
Question #: 26
Topic #: 7
[All CIMAPRA19-E02-1 Questions]

An experienced IT project manager provides the following advice about planning a new project:

"The project should start withaRequirements Analysis which should take 10 days. When this is finished Detailed Design (10 days) and Interface studies (15 days) can start at the same time. As soon as they are both complete Prototyping can start (30 days).

Prototyping is the predecessor of both Implementation (10 days) and Data Conversion (20 days).

Go-Live is the final activity (5 days) and follows when Implementation and Data Conversion are both complete."

Using critical path analysis which statements are correct.

Select ALL that apply.

Show Suggested Answer Hide Answer
Suggested Answer: A, B

Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel