CIMAPRA19-E02-1 Exam - Topic 5 Question 122 Discussion

A small project has been planned based on the following set of activities:Apply critical path analysis and identify the correct statement:The critical path runs through A,B,D,E and C has 2 days of float (free slack)
A) The critical path runs through A,B,D,E and C has 6 days of float (free slack)
B) The critical path runs through A,C,E and B has 5 days of float (free slack)
C) The critical path runs through A,C,E and D has 4 days of float (free slack)

CIMAPRA19-E02-1 Exam - Topic 5 Question 122 Discussion

Actual exam question for CIMA's CIMAPRA19-E02-1 exam
Question #: 122
Topic #: 5
[All CIMAPRA19-E02-1 Questions]

A small project has been planned based on the following set of activities:

Apply critical path analysis and identify the correct statement:

The critical path runs through A,B,D,E and C has 2 days of float (free slack)

Show Suggested Answer Hide Answer
Suggested Answer: A

<table version='1.0' width='245' border='1' bgcolor='#FFFFFF' >

<colgroup

width='70' />

<colgroup

width='70' />

<colgroup

width='105' />

<thead >

<tr>

<th >

<font face='Arial' size='11'>Activity</font>

</th>

<th >

<font face='Arial' size='11'>Duration</font>

</th>

<th >

<font face='Arial' size='11'>Predecessor/s</font>

</th>

</tr>

</thead>

<tbody >

<tr >

<td >

<font face='Arial' size='11'>A</font>

</td>

<td >

<font face='Arial' size='11'> 2 days</font>

</td>

<td >

<font face='Arial' size='11'>- </font>

</td>

</tr>

<tr >

<td >

<font face='Arial' size='11'>B</font>

</td>

<td >

<font face='Arial' size='11'> 5 days</font>

</td>

<td >

<font face='Arial' size='11'> A</font>

</td>

</tr>

<tr >

<td >

<font face='Arial' size='11'>C</font>

</td>

<td >

<font face='Arial' size='11'> 6 days</font>

</td>

<td >

<font face='Arial' size='11'> A</font>

</td>

</tr>

<tr >

<td >

<font face='Arial' size='11'>D</font>

</td>

<td >

<font face='Arial' size='11'> 3 days</font>

</td>

<td >

<font face='Arial' size='11'> B</font>

</td>

</tr>

<tr >

<td >

<font face='Arial' size='11'>E</font>

</td>

<td >

<font face='Arial' size='11'> 1 day</font>

</td>

<td >

<font face='Arial' size='11'> C,D</font>

</td>

</tr>

</tbody>

</table>


Contribute your Thoughts:

0/2000 characters
Nettie
3 days ago
I feel confused. Why would C have 6 days of float?
upvoted 0 times
...
Laurena
8 days ago
I think the answer is A. It makes sense with the float.
upvoted 0 times
...
Leonida
13 days ago
I feel like A,C,E could be a trick option.
upvoted 0 times
...
Donte
19 days ago
C has 2 days of float sounds right to me.
upvoted 0 times
...
Stephen
24 days ago
I agree, but I’m not sure about the float days.
upvoted 0 times
...
Gerald
29 days ago
I think the critical path is A,B,D,E.
upvoted 0 times
...
Teddy
1 month ago
I agree with Alice. A,B,D,E makes sense for the critical path.
upvoted 0 times
...
Lai
1 month ago
I feel like option B is misleading. A,C,E doesn't seem right.
upvoted 0 times
...
Toi
1 month ago
But what about option A? It says C has 6 days of float.
upvoted 0 times
...
Winfred
2 months ago
I think the critical path is A,B,D,E.
upvoted 0 times
...
Venita
2 months ago
I thought float only applies to non-critical activities?
upvoted 0 times
...
Tayna
2 months ago
Definitely not B, that path doesn't make sense.
upvoted 0 times
...
Broderick
4 months ago
Wait, how does C have float if it's not on the critical path?
upvoted 0 times
...
Arlie
4 months ago
I agree, but C having 2 days of float seems off.
upvoted 0 times
...
Mona
4 months ago
The critical path is A,B,D,E for sure.
upvoted 0 times
...
Delpha
4 months ago
I thought float only applies to non-critical activities?
upvoted 0 times
...
Apolonia
4 months ago
Definitely not B, that path doesn't make sense.
upvoted 0 times
...
Karina
4 months ago
Wait, how does C have float if it's not on the critical path?
upvoted 0 times
...
Mitsue
5 months ago
I agree, but C having 2 days of float seems off.
upvoted 0 times
...
Luther
5 months ago
The critical path is A,B,D,E for sure.
upvoted 0 times
...
Regenia
5 months ago
I feel like option A is the most likely correct answer since it mentions the critical path we identified in class, but I’m not completely confident about the float days.
upvoted 0 times
...
Teddy
5 months ago
I vaguely recall that float is calculated based on the total duration, but I can't remember how to apply it to this specific question.
upvoted 0 times
...
Natalie
5 months ago
I think the critical path is definitely A,B,D,E based on the dependencies we discussed, but I’m confused about the float calculations.
upvoted 0 times
...
Pansy
5 months ago
I remember we practiced a similar question where we had to identify the critical path, but I’m not sure if it was the same activities.
upvoted 0 times
...