New Year Sale 2026! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

CIMAPRA19-E02-1 Exam - Topic 5 Question 121 Discussion

Actual exam question for CIMA's CIMAPRA19-E02-1 exam
Question #: 121
Topic #: 5
[All CIMAPRA19-E02-1 Questions]

A project manager is calculating the budget cost of a single project task called "Server Configuration".

This task isestimated to last 8 weeks and requires the full-time services of two software consultants, both for the entire duration of the task.

One consultant commands an inclusive rate of $400/day and the other $40/hour based on an eight hour day. Fixed hardware costs of $12,000 have also been estimated for the task.

Calculate the total budget cost for the task (ignoring any other resources or costs) - assuming a five day working week.

Give your answer as a whole number.

The total cost is$ .

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

0/2000 characters
Meghan
5 days ago
I practiced a similar question where we had to calculate costs based on different rates, so I think we just need to sum everything up after finding the total for each consultant.
upvoted 0 times
...
Horace
10 days ago
I think I remember that we need to calculate the daily cost for both consultants first, but I'm not sure how to convert the hourly rate for the second one.
upvoted 0 times
...
Agustin
15 days ago
Wait, I'm still not sure I understand how to calculate the total cost. Can someone walk me through it step-by-step? I want to make sure I have the right approach before submitting my answer.
upvoted 0 times
...
Clarinda
20 days ago
Okay, I'm pretty confident I can solve this. Let me just double-check the math... Yep, I think Helaine has the right approach. This seems straightforward enough.
upvoted 0 times
...
Helaine
26 days ago
I think I've got this. For the first consultant at $400/day, the total cost is 40 days x $400 = $16,000. For the second consultant at $40/hour and 8 hours/day, the total cost is 40 days x 8 hours/day x $40/hour = $12,800. Add the $12,000 hardware costs and the total budget cost is $40,800.
upvoted 0 times
...
Daisy
1 month ago
Hmm, I'm a bit confused. Do we need to convert the hourly rate to a daily rate for the second consultant? And how do we factor in the full-time requirement for both consultants?
upvoted 0 times
...
Yoko
1 month ago
Okay, let's break this down step-by-step. We have two consultants, one at $400/day and the other at $40/hour. The task is 8 weeks long, with a 5-day work week, so that's 40 days total. We need to calculate the cost for each consultant and add the fixed hardware costs.
upvoted 0 times
...

Save Cancel