A project manager is calculating the budget cost of a single project task called "Server Configuration".
This task isestimated to last 8 weeks and requires the full-time services of two software consultants, both for the entire duration of the task.
One consultant commands an inclusive rate of $400/day and the other $40/hour based on an eight hour day. Fixed hardware costs of $12,000 have also been estimated for the task.
Calculate the total budget cost for the task (ignoring any other resources or costs) - assuming a five day working week.
Give your answer as a whole number.
The total cost is$ .
Jesus
1 month agoFelix
2 months agoCeola
2 months agoPage
2 months agoLynsey
4 months agoEric
4 months agoLavonna
4 months agoZona
4 months agoThaddeus
4 months agoLyndia
4 months agoAllene
5 months agoVi
5 months agoTomas
5 months agoAlida
5 months agoGenevieve
5 months agoJessenia
5 months agoMeghan
6 months agoHorace
6 months agoAgustin
7 months agoClarinda
7 months agoHelaine
7 months agoDaisy
7 months agoYoko
7 months agoBarney
13 days agoJacklyn
19 days agoEna
24 days agoIola
29 days agoBarney
1 month agoJacklyn
1 month ago