Your organization has decided to change the default scheduling strategy to be used as a starting point when creating an Assignment on the Project.
Which of the following tasks do you need to perform to accommodate this requirement?
To change the default scheduling strategy used when creating an assignment on a project:
Navigate to Configuration Options:
Go to App Launcher in Salesforce.
Search for and open PSA Administration.
Locate Configuration Options.
Find the Scheduling Configuration Group:
Look for the configuration group related to Scheduling.
Open the Configuration Value record for Scheduling.
Adjust the Default Scheduling Strategy:
Modify the Default Scheduling Strategy to the new preferred value.
Save changes.
Test the Configuration:
Create a new Assignment on a Project.
Verify that the new default scheduling strategy is applied.
PSA System Administration Guide
Certinia PSA Data Dictionary and Configuration Guide
Rupert
2 months agoDelpha
2 months agoBrittni
3 months agoValentine
3 months agoTonette
3 months agoTom
3 months agoShala
4 months agoFiliberto
4 months agoPenney
4 months agoLeigha
4 months agoPatria
4 months agoAlica
5 months agoBen
5 months ago