Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

BICSI Exam RCDDv14.1 Topic 3 Question 53 Discussion

Actual exam question for BICSI's RCDDv14.1 exam
Question #: 53
Topic #: 3
[All RCDDv14.1 Questions]

An ICT distribution designer is representing a client during a project execution. What is the designer's role in the Vendor and Contractor Coordination?

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

Elouise
7 days ago
Wait, hold up. Where's the option for the designer to do the hokey-pokey and turn themselves around? That's what it's all about, right?
upvoted 0 times
...
Dong
8 days ago
Hmm, B seems like the obvious choice. The designer is the traffic cop, keeping all those subcontractors from running into each other. Gotta stay on top of that schedule!
upvoted 0 times
...
Jaime
9 days ago
D is the way to go! The designer should submit RFIs to address any coordination issues with other trades. That's the most proactive approach.
upvoted 0 times
Nathan
23 hours ago
A) Oversee the sequence of the work and ensure that the job proceeds as anticipated in accordance with the project execution schedule
upvoted 0 times
...
...
Terrilyn
23 days ago
I think option C is more comprehensive. The designer should hold two critical meetings to introduce all parties and set the tone for the project.
upvoted 0 times
...
Leota
25 days ago
B is the correct answer. The designer's role is to coordinate the daily activities of all trades through regular meetings, not just oversee the sequence of work.
upvoted 0 times
Mauricio
8 days ago
C) Holds two critical meetings to begin the project and allow all parties to introduce themselves
upvoted 0 times
...
Vallie
18 days ago
B) Synchronizes the daily activities of all trades through daily or weekly meetings (depending on project size, complexity, or criticality) with individual trade PMs. Fore people, supervisors and designers as necessary
upvoted 0 times
...
Blossom
19 days ago
A) Oversee the sequence of the work and ensure that the job proceeds as anticipated in accordance with the project execution schedule
upvoted 0 times
...
...
Tien
1 months ago
I believe the designer should also hold critical meetings at the beginning of the project to introduce all parties involved.
upvoted 0 times
...
Judy
2 months ago
I agree with Frankie. The designer should also submit RFIs to the GC if there are any coordination issues.
upvoted 0 times
...
Frankie
2 months ago
I think the designer's role is to oversee the sequence of work and ensure it proceeds as planned.
upvoted 0 times
...

Save Cancel