Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

BICSI Exam RCDDv14.1 Topic 3 Question 35 Discussion

Actual exam question for BICSI's RCDDv14.1 exam
Question #: 35
Topic #: 3
[All RCDDv14.1 Questions]

The above performance report shows the earned value (EV) analysis for a program The program director performs a high-level analysis and must present a summary narrative to the steering committee

What do the current findings show?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Bethanie
1 months ago
Wow, this question is like a puzzle. I bet the steering committee is going to be so impressed when the program director nails this summary. Gotta love those high-lBethaniel analyses!
upvoted 0 times
...
Kimi
1 months ago
Oof, this is a tough one. Earned value analysis can be a real mind-bender. I'm going to have to really think this through before answering. Maybe I should just guess and hope for the best, like Dwight.
upvoted 0 times
...
Dwight
1 months ago
Ha! This is the kind of question that makes me want to pull my hair out. I always struggle with earned value concepts. I'm going to guess option A and hope for the best.
upvoted 0 times
Marguerita
7 days ago
Looks like Project A is running behind schedule and is over budget, while projects B, C, and D are on schedule.
upvoted 0 times
...
Ahmad
15 days ago
The overall program is actually performing within an acceptable level of variance.
upvoted 0 times
...
Eura
16 days ago
I agree, Project A is running ahead of schedule and is under budget, while projects B, C and D are behind schedule.
upvoted 0 times
...
Cortney
22 days ago
I think the current findings show that Project C is running behind schedule and is over budget, projects A, B and D are on schedule.
upvoted 0 times
...
...
Rolland
2 months ago
I'm not sure about this one. The report is a bit vague, and there could be multiple ways to interpret the data. I'm leaning towards option B, but I'd have to do some more analysis to be confident.
upvoted 0 times
Donette
26 days ago
I agree, the report is not very clear, we should definitely do more analysis.
upvoted 0 times
...
Tammara
1 months ago
I think we need to dig deeper into the data before making a decision.
upvoted 0 times
...
...
Hector
2 months ago
Hmm, this seems like a tricky question. Let's see, the report shows the earned value analysis, so we need to look at the schedule and cost variances. I think option C might be the correct answer, as the overall program appears to be within an acceptable level of variance.
upvoted 0 times
...
Amie
2 months ago
I disagree, I believe that Project A is actually running ahead of schedule and under budget. The other projects are the ones facing delays.
upvoted 0 times
...
Jutta
2 months ago
I agree with Ma, Project C seems to be causing some issues. But overall, the program is still within an acceptable level of variance.
upvoted 0 times
...
Ma
2 months ago
I think the current findings show that Project C is running behind schedule and is over budget, while projects A, B, and D are on schedule.
upvoted 0 times
...

Save Cancel