New Year Sale 2026! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

BICSI RCDDv14.1 Exam - Topic 1 Question 31 Discussion

Actual exam question for BICSI's RCDDv14.1 exam
Question #: 31
Topic #: 1
[All RCDDv14.1 Questions]

Which of the following serves as a guiding principle for a program manager when preparing a program work breakdown structure?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

0/2000 characters
Bulah
3 months ago
Really? I thought it was all about resources, not just control.
upvoted 0 times
...
Mona
3 months ago
D is crucial too, control is everything!
upvoted 0 times
...
Coral
3 months ago
C seems a bit too technical for most programs.
upvoted 0 times
...
Isaiah
4 months ago
Agreed, B makes the most sense for clarity.
upvoted 0 times
...
Iola
4 months ago
I think it's definitely B, work package level is key.
upvoted 0 times
...
Cary
4 months ago
I lean towards A, but I remember discussing how resources shouldn't be the primary focus when breaking down work.
upvoted 0 times
...
Shaun
4 months ago
I feel like C could be relevant since the architecture baseline is crucial, but I can't recall if it's the main guiding principle.
upvoted 0 times
...
Kimberlie
4 months ago
I remember practicing a question similar to this, and I think B was the right choice there. But I'm not confident if it applies here too.
upvoted 0 times
...
Johnathon
5 months ago
I think the answer might be D, but I'm not entirely sure. It seems like control is really important in project management.
upvoted 0 times
...
Kassandra
5 months ago
Hmm, this is a tricky one. I'm not 100% sure, but I think the key is to decompose the program to the appropriate level to achieve the necessary control and oversight. I'll go with option D and hope for the best.
upvoted 0 times
...
Kyoko
5 months ago
I've got a good handle on work breakdown structures from my project management courses. I believe the right approach is to decompose the program to the level that will allow the program manager to effectively manage and control the work. Option D seems like the best fit.
upvoted 0 times
...
Quentin
5 months ago
I'm a bit confused on this one. Is it asking about the level of detail in the work breakdown structure? I'm not totally sure which option best captures the guiding principle.
upvoted 0 times
...
Eden
5 months ago
Okay, let's see. I think the key here is to focus on the level of decomposition that will provide the right level of control and oversight for the program. I'll go with option D.
upvoted 0 times
...
Delfina
5 months ago
Hmm, this seems like a tricky one. I'll need to think carefully about the key principles of program management to figure this out.
upvoted 0 times
...
Dolores
5 months ago
This is similar to a question we practiced where the answer was "key." So, "secret" makes sense but I'm unsure.
upvoted 0 times
...
Leonard
5 months ago
I'm not sure about this one. I might need to ask the instructor for some clarification before attempting to answer.
upvoted 0 times
...
Diego
5 months ago
Okay, I think I've got this. The question is asking for two correct answers, so I'll go with options C and D. Bundling the Inception network in a Docker container or using custom code with TensorFlow Estimator seem like the best ways to incorporate the Inception architecture.
upvoted 0 times
...
Olga
5 months ago
I vaguely remember something about how cost management is a bigger concern in private clouds, but I'm not entirely sure.
upvoted 0 times
...
Earlean
10 months ago
Haha, A? What is this, a game of Tetris? D is the only sensible choice here. Gotta keep that program under control, am I right?
upvoted 0 times
Yvette
9 months ago
D) Decompose the program at a level sufficient to achieve control
upvoted 0 times
...
Ammie
9 months ago
B) Decompose the program to the work package level
upvoted 0 times
...
Lashawn
9 months ago
A) Decompose the program work based upon available resources
upvoted 0 times
...
...
Audra
10 months ago
Option A? Really? I mean, basing the work breakdown on available resources seems like putting the cart before the horse. D is clearly the way to go.
upvoted 0 times
Chaya
8 months ago
It's important to decompose the program at a level that allows for effective control.
upvoted 0 times
...
Mabelle
9 months ago
Decomposing the program at a level sufficient to achieve control makes sense.
upvoted 0 times
...
Veda
9 months ago
I agree, option D is the best choice for achieving control.
upvoted 0 times
...
...
Novella
10 months ago
I'm torn between B and D, but I'll go with D since it seems to strike the right balance between granularity and control.
upvoted 0 times
Jacki
9 months ago
D is definitely the way to go for control and granularity.
upvoted 0 times
...
Roosevelt
9 months ago
B might be too detailed, D is a good compromise.
upvoted 0 times
...
Janine
9 months ago
I agree, D seems like the most balanced option.
upvoted 0 times
...
Van
9 months ago
I think D is the best choice for achieving control.
upvoted 0 times
...
...
Raina
10 months ago
I believe decomposing the program at a level sufficient to achieve control is the key.
upvoted 0 times
...
Tran
11 months ago
Hmm, I think the correct answer is D. Decomposing the program at a level sufficient to achieve control seems like the most logical approach.
upvoted 0 times
Alethea
9 months ago
Yes, decomposing the program at a level sufficient to achieve control is key.
upvoted 0 times
...
Lucia
9 months ago
I agree, D does seem like the most logical choice.
upvoted 0 times
...
...
Sueann
11 months ago
I agree with Fausto, decomposing the program to the work package level helps in achieving control.
upvoted 0 times
...
Fausto
11 months ago
I think the guiding principle is to decompose the program to the work package level.
upvoted 0 times
...

Save Cancel