BCS TM3 Exam - Topic 3 Question 15 Discussion

Posted by Salley on Jun 17, 2026 at 11:28 PM

Test control uses the information from test monitoring to provide guidance and take corrective action when required.

Which of the following is not a possible test control action?

Suggested Answer: C

Get Premium TM3 Questions as Interactive Web-Based Practice Test or PDF Real Exam Format Detailed Explanations Instant Access Get Your Practice Test
15 comments · newest first
AL
Alesia 2 months ago
Fulfilment checks are just assessments, not controls.
DE
Deeanna 2 months ago
Right! Adding resources is also a control action.
JU
Junita 2 months ago
Exactly! Re-prioritisation and adjusting schedules are actions.
AL
Alesia 2 months ago
C seems like the right choice. It’s more about evaluation, not control.
DE
Deeanna 2 months ago
Yeah, I’m leaning towards C.
JU
Junita 3 months ago
I think this question is tricky.
LO
Loreen 3 months ago
I’m surprised this is even a question!
XO
Xochitl 3 months ago
Wait, checking exit criteria isn’t a control action? That seems off.
DO
Dong 3 months ago
Totally agree with A and B being valid actions!
TA
Tamie 3 months ago
I think D could be a control action too.
PU
Pura 3 months ago
C is definitely not a control action.
MI
Mitsue 4 months ago
I recall discussing how re-prioritising test cases and adjusting schedules are common control actions, but I’m not certain about the role of checking exit criteria in this context.
AL
Alesia 4 months ago
I’m a bit confused about this one. I thought all of these could be considered control actions, but maybe adding resources isn’t really a control action?
CA
Carmen 4 months ago
I feel like we practiced a similar question where adjusting the schedule was considered a control action, so I might lean towards option C being the answer.
AH
Ahmed 4 months ago
I think I remember that test control actions are meant to help keep the testing process on track, but I'm not sure if checking exit criteria counts as an action.
0/2000 characters

Save Cancel