To which category of cost of quality does "fixing a defect found during testing" belong?
Your company is considering purchasing a test tool suite from a respectable vendor. Your manager has searched the internet for comparable
products, but none of them meet his specific requirements. A tool demonstration has been arranged for next week and your team has been
invited to attend. The tool suite consists of a test management tool, test execution tool, and a requirements management tool. There is a
possibility of adding a performance testing tool at a later stage.
You have decided to attend the demo but raise some issues beforehand regarding expectations.
Which two issues from the options provided below should at least be raised?
Your company is considering purchasing a test tool suite from a respectable vendor. Your manager has searched the internet for comparable
products, but none of them meet his specific requirements. A tool demonstration has been arranged for next week and your team has been
invited to attend. The tool suite consists of a test management tool, test execution tool, and a requirements management tool. There is a
possibility of adding a performance testing tool at a later stage.
You have decided to attend the demo but raise some issues beforehand regarding expectations.
Which two issues from the options provided below should at least be raised?
You are a test manager developing a master test plan. As part of the master test plan, you are defining exit criteria for the various test levels.
Which of the following exit criteria would be most appropriate and SMART for component testing, and which one would be most appropriate and SMART for system testing?
i. 95% of the tests prepared are executed successfully
ii. All test cases have been run
iii. 80% decision coverage for all tests run
iv. At least 30 defects have been found
v. At least two weeks of test execution
vi. No more open defects
Three exit criteria have been defined for a project:
A: Test cases passed is more than 70%
B: Number of outstanding defects is less than 5
C: Number of defects per test case is less than 0.5
The first week of the testing has shown the following results:
Evaluate the status of the project against the defined exit criteria.
Tiffiny
14 hours agoLindsay
9 days agoVal
16 days agoKarma
23 days agoDalene
1 month agoAlaine
1 month agoCasie
2 months agoTawanna
2 months agoAudrie
2 months agoVanesa
2 months agoBarney
3 months agoGeorgeanna
3 months agoAngella
3 months agoGaynell
3 months agoQuentin
3 months agoEileen
4 months agoCarman
4 months ago