Three exit criteria have been defined for a project:
A: Test cases passed is more than 70%
B: Number of outstanding defects is less than 5
C: Number of defects per test case is less than 0.5
The first week of the testing has shown the following results:
Evaluate the status of the project against the defined exit criteria.
Suggested Answer: B
Get Premium TM3 Questions
as Interactive Web-Based Practice Test or PDF
Real Exam Format
Detailed Explanations
Instant Access
Get Your Practice Test
31 comments · newest first
AN
Anglea
6 months ago
But we can't ignore the defects in B and C.
JU
Julian
6 months ago
I agree with Jolanda. A shows success!
HE
Helene
6 months ago
I lean towards option D. Nothing looks good.
CH
Chi
7 months ago
Option C seems likely. One passed, two failed.
GL
Glenna
7 months ago
I feel option B is realistic. Two criteria failed.
JO
Jolanda
7 months ago
I think option A is the best choice. All criteria met!
FL
Floyd
7 months ago
I'm surprised by these results! Thought we were doing better.
LA
Laticia
8 months ago
Wait, how can A be OK if B is not?
YO
Youlanda
8 months ago
C seems fine, but A and B are a mess.
PA
Paola
8 months ago
I think B is also not OK.
TA
Tanesha
8 months ago
Criteria A is definitely not OK.
PA
Paola
8 months ago
Wait, is this a trick question? I feel like I'm missing something... *scratches head*
AL
Aleisha
9 months ago
D seems like the obvious choice here. Can't have all three criteria failing, that's a big no-no!
LA
Lawrence
9 months ago
I’m a bit confused about how to interpret the results. If A is OK but B and C are not, does that mean we can still proceed? I need to review that part again.
ST
Stevie
9 months ago
I think if criteria B and C are not met, it could really impact the project timeline. I need to recall how we calculated defects per test case.
DE
Deandrea
9 months ago
I remember we practiced a similar question where we had to evaluate exit criteria based on test results. I think I need to double-check the numbers for each criterion.
RE
Remona
9 months ago
Alright, I got this. I just need to go through each criteria, check if the results meet the requirements, and then select the appropriate answer. Piece of cake!
SC
Scarlet
9 months ago
This seems like a tricky one. I'm not sure I fully understand how to interpret the criteria and the results. I might need to ask the instructor for some clarification before attempting to answer.
KR
Kristofer
10 months ago
Okay, let's see. We have three criteria, and the results for the first week. I just need to match up the criteria with the results and select the right answer. Shouldn't be too hard.
KE
Kenneth
10 months ago
Uh oh, looks like the team has some work to do. Time to get those defects under control!
JO
Jose
10 months ago
Okay, let's see... Criteria A is met, but B and C are not. Gotta love these project management puzzles!
LA
Latricia
10 months ago
Hmm, looks like we've got a tricky one here. Time to put on my thinking cap!
AR
Arletta
10 months ago
I feel like criteria A is usually the easiest to meet, but I’m not sure about the others. I hope we have fewer than 5 defects!
NE
Nell
11 months ago
Haha, this reminds me of that time we had a bug that turned all our test cases into unicorns. Good times!
CA
Carlee
11 months ago
I'm a bit confused by the wording of the criteria. Do I need to check all three, or just one of them? I'll have to read through it carefully.
LI
Lina
11 months ago
Hmm, this looks like a straightforward question about evaluating project exit criteria. I think I can handle this one.
MA
Ma
5 months ago
True, we need to double-check the defects.
SA
Sanda
5 months ago
Criteria B being OK is crucial.
EM
Emerson
6 months ago
But what if we missed something?
JA
Jacquelyne
6 months ago
Yeah, all criteria are met!
MA
Marjory
6 months ago
I think option A is the best choice.