Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

BCS Exam TM12 Topic 8 Question 42 Discussion

Actual exam question for BCS's TM12 exam
Question #: 42
Topic #: 8
[All TM12 Questions]

The following are the exit criteria described in the test plan of a software product:

EX1. The test suite for the product must ensure that at least each quality risk item is covered by at least one test case (a quality risk item can be covered by more test cases).

EX2. All test cases in the test suite must be run during the execution phase.

EX3. Defects are classified into two categories: ''C'' (critical defect) and ''NC'' (non-critical defect). No known C defects shall exist in the product at the end of the test execution phase.

Which of the following information is useless when the specified exit criteria is evaluated?

Number of correct responses: 1

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel