BCS TM12 Exam - Topic 5 Question 129 Discussion
You are estimating the effort for the integration testing activities of a new project. Consider the following factors, which can affect that estimation:Availability of re-usable test systems and documentation from previous, similar projectsUnexpected timing of components arrivalStability of the integration test team (no turnover)Many and geographically distributed sub-teamsWhich of the following statements is true?Number of correct responses: 1
C) II. and IV. can negatively affect the estimationI.
and III. usually favor the accuracy of the estimation effort
A) I. and II. can negatively affect the estimation
III. and IV. usually favor the accuracy of the estimation effort
B) II. and III. can negatively affect the estimationI.
and IV. usually favor the accuracy of the estimation effort
D) III. and IV. can negatively affect the estimationI.
and II. usually favor the accuracy of the estimation effort
Louvenia
1 day agoMarci
7 days agoDorothy
12 days agoDaniela
17 days agoSherron
22 days agoAlishia
27 days agoRenay
1 month agoInes
1 month agoEugene
1 month agoGilma
2 months agoYesenia
2 months agoYun
2 months agoChantell
2 months agoMelissa
2 months agoDelsie
2 months agoAlisha
3 months agoVeronika
3 months agoMicah
3 months ago