You are estimating the effort for the integration testing activities of a new project. Consider the following factors, which can affect that estimation:Availability of re-usable test systems and documentation from previous, similar projectsUnexpected timing of components arrivalStability of the integration test team (no turnover)Many and geographically distributed sub-teamsWhich of the following statements is true?Number of correct responses: 1
C) II. and IV. can negatively affect the estimationI. and III. usually favor the accuracy of the estimation effort
A) I. and II. can negatively affect the estimation III. and IV. usually favor the accuracy of the estimation effort
B) II. and III. can negatively affect the estimationI. and IV. usually favor the accuracy of the estimation effort
D) III. and IV. can negatively affect the estimationI. and II. usually favor the accuracy of the estimation effort

BCS TM12 Exam - Topic 5 Question 129 Discussion

Actual exam question for BCS's TM12 exam
Question #: 129
Topic #: 5
[All TM12 Questions]

You are estimating the effort for the integration testing activities of a new project. Consider the following factors, which can affect that estimation:

Availability of re-usable test systems and documentation from previous, similar projects

Unexpected timing of components arrival

Stability of the integration test team (no turnover)

Many and geographically distributed sub-teams

Which of the following statements is true?

Number of correct responses: 1

Show Suggested Answer Hide Answer
Suggested Answer: C