Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

BCS TM12 Exam - Topic 3 Question 125 Discussion

After the presentation, you are asked to explain the chart.Assume you have applied a full risk-based testing strategy.Which of the following answers would you expect to best describe the pie chart?Number of correct responses: 1
C) Only the lowest-risk items, tests and bugs should remain in the blue and red areas. Therefore the application can be released at any time subject to management of the items identified in those areas
A) All the risk items have been covered with tests. No more risk items remain to test
B) According to the full risk-based testing strategy applied, it is very likely that the highest-risk items, tests and bugs remain in the blue and red areas. Therefore, it is very risky to release the application
D) 97 percent of the risk items has been tested. No open bugs or test failures remain. Only 3 percent of risk items remains to be covered by the remaining test

BCS TM12 Exam - Topic 3 Question 125 Discussion

Actual exam question for BCS's TM12 exam
Question #: 125
Topic #: 3
[All TM12 Questions]

After the presentation, you are asked to explain the chart.

Assume you have applied a full risk-based testing strategy.

Which of the following answers would you expect to best describe the pie chart?

Number of correct responses: 1

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

0/2000 characters
Earleen
1 hour ago
Right, we need to address those high risks first.
upvoted 0 times
...
Shay
5 days ago
Exactly, better safe than sorry!
upvoted 0 times
...
Tyisha
10 days ago
Only 3% left? Still too much uncertainty.
upvoted 0 times
...
Arthur
16 days ago
I like option D, but it feels incomplete.
upvoted 0 times
...
Fatima
21 days ago
Yeah, not all risks can be covered.
upvoted 0 times
...
Ligia
26 days ago
Option A sounds too optimistic.
upvoted 0 times
...
Shay
1 month ago
I agree, releasing now seems risky.
upvoted 0 times
...
Earleen
1 month ago
The blue and red areas indicate high risk.
upvoted 0 times
...
Fatima
1 month ago
Why do you feel that way?
upvoted 0 times
...
Earleen
2 months ago
I think option B is the best choice.
upvoted 0 times
...
Lawanda
2 months ago
D sounds too optimistic, I doubt all bugs are really fixed.
upvoted 0 times
...
Hillary
2 months ago
C seems way off, we can't just ignore the high-risk areas!
upvoted 0 times
...
Alesia
2 months ago
Wait, are we sure 97% is enough?
upvoted 0 times
...
Larae
2 months ago
I totally agree, releasing now would be risky!
upvoted 0 times
...
Paris
2 months ago
Looks like B is the most accurate based on the chart.
upvoted 0 times
...
Denny
3 months ago
I feel like option A is too optimistic. Just because all items are covered doesn't mean they were tested thoroughly, right?
upvoted 0 times
...
Theodora
4 months ago
I'm a bit confused about option D; it sounds good, but if only 3 percent of risk items are left, does that mean we can release?
upvoted 0 times
...
Hoa
4 months ago
I remember a practice question similar to this where we discussed how risk-based testing prioritizes high-risk areas, so I lean towards option B as well.
upvoted 0 times
...
Glory
4 months ago
I think option B makes the most sense because it highlights that the highest-risk items are still untested, but I'm not completely sure.
upvoted 0 times
...

Save Cancel