Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

BCS Exam TM12 Topic 2 Question 63 Discussion

Actual exam question for BCS's TM12 exam
Question #: 63
Topic #: 2
[All TM12 Questions]

Assume you have some data related to confirmation testing during system testing of a past project.

In that project 240 bug reports have been opened once, 80 were opened twice, 10 were opened three times and no bug reports have been opened more than three times.

You estimate that a bug report, which has failed its confirmation test, costs, on average, 3 person-hours.

Which of the following statements correctly describe the value of these confirmatory testing activities based on cost of quality?

Number of correct responses: 1

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel