BCS ISEB-PM1 Exam - Topic 7 Question 25 Discussion

Posted by Jesusa on May 10, 2022 at 03:18 AM

The project team reviews identified risks and the risk response strategy. For one of the risks, the team realizes that the implementation of the risk response would generate another risk. This new risk is which of the following types of risk?

Suggested Answer: A

Get Premium ISEB-PM1 Questions as Interactive Web-Based Practice Test or PDF Real Exam Format Detailed Explanations Instant Access Get Your Practice Test
7 comments · newest first
DO
Domingo 11 months ago
Primary risks are the original ones, so it can't be that.
JE
Jennie 12 months ago
Residual risks are different, right?
CO
Cory 12 months ago
Wait, are we sure it's not a tertiary risk?
MI
Mira 12 months ago
Totally agree, secondary is the right term here.
AL
Alverta 1 year ago
It's definitely a secondary risk!
MI
Mirta 1 year ago
Okay, let's see. Designated ports are the ports that are selected to forward traffic on a segment, so it makes sense that there would be one per segment. I'll go with option B.
SH
Shawn 1 year ago
I'm a bit confused about the statement on creating synonyms for sequences. I'll have to double-check that one.
0/2000 characters

Save Cancel