A project has seven activities: A, B, C, D, E, F, and G. Activities A, B, and D can start anytime. Activity A takes 3 weeks, Activity B takes 5 weeks, and Activity D takes 11 weeks. Activities A and B must be completed before Activity C can start. Activity C requires 6 weeks to complete. Activities B, C, and D must be completed before Activity E can start. Activity E requires 2 weeks. Activity F takes 4 weeks and can start as soon as Activity C is completed. Activity E must be completed before Activity G starts. Activity G requires 3 weeks. Activities F and G must be completed for the project to be completed. Which activities have float available?
Jill
7 months agoLeanna
7 months agoRebeca
7 months agoAlaine
7 months agoPolly
7 months agoDaron
8 months agoChaya
8 months agoKindra
8 months agoSylvie
8 months agoSalley
8 months agoAnabel
8 months agoLindsey
8 months agoDaron
8 months agoSalley
1 year agoElke
1 year agoElena
1 year agoBasilia
1 year agoHelaine
1 year agoKarl
1 year agoLuis
1 year agoYolando
1 year agoLeota
1 year agoMagdalene
1 year agoLouvenia
1 year agoLuisa
1 year agoNichelle
1 year agoSelma
1 year agoCletus
1 year agoAnnice
1 year ago