BCS ISEB-PM1 Exam - Topic 6 Question 94 Discussion

Actual exam question for BCS's ISEB-PM1 exam
Question #: 94
Topic #: 6
[All ISEB-PM1 Questions]

A project has seven activities: A, B, C, D, E, F, and G. Activities A, B, and D can start anytime. Activity A takes 3 weeks, Activity B takes 5 weeks, and Activity D takes 11 weeks. Activities A and B must be completed before Activity C can start. Activity C requires 6 weeks to complete. Activities B, C, and D must be completed before Activity E can start. Activity E requires 2 weeks. Activity F takes 4 weeks and can start as soon as Activity C is completed. Activity E must be completed before Activity G starts. Activity G requires 3 weeks. Activities F and G must be completed for the project to be completed. Which activities have float available?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

0/2000 characters
Jill
4 months ago
Activity A has eight weeks float? That seems off!
upvoted 0 times
...
Leanna
4 months ago
Nope, there’s no float available in the project.
upvoted 0 times
...
Rebeca
4 months ago
Wait, how does A have float? I thought it was tight on schedule.
upvoted 0 times
...
Alaine
5 months ago
I agree, that sounds right!
upvoted 0 times
...
Polly
5 months ago
Activity A has two weeks float, activity F has one week.
upvoted 0 times
...
Daron
5 months ago
Activity A seems like it could have a lot of float, maybe eight weeks? I need to double-check my calculations.
upvoted 0 times
...
Chaya
5 months ago
I practiced a question where there was no float available, so I'm leaning towards that for this one, but it feels off.
upvoted 0 times
...
Kindra
5 months ago
I think Activity F definitely has some float, but I can't recall if it's just one week or more.
upvoted 0 times
...
Sylvie
6 months ago
I remember calculating float for similar questions, but I'm not sure about the exact float for Activity A.
upvoted 0 times
...
Salley
6 months ago
I've got a strategy for this - I'll start by identifying the critical path, then work backwards from the end to figure out the float for the other activities. Shouldn't be too hard if I stay organized.
upvoted 0 times
...
Anabel
6 months ago
Whoa, this is a lot of information to process. I better read through it a few times to make sure I understand all the relationships between the activities before I try to solve this.
upvoted 0 times
...
Lindsey
6 months ago
Okay, let me think this through step-by-step. I know I need to identify the critical path and then calculate the float for the other activities. Time to get out my pen and paper!
upvoted 0 times
...
Daron
6 months ago
Hmm, this looks like a tricky critical path question. I'll need to carefully map out the dependencies and durations to determine which activities have float.
upvoted 0 times
...
Salley
11 months ago
Wait, did they say Activity G requires 3 weeks? I thought it was a trick question and the answer was 4 weeks. Dang it!
upvoted 0 times
Elke
10 months ago
I believe Activity A has two weeks float and Activity F has one week.
upvoted 0 times
...
Elena
10 months ago
So, which activities do you think have float available?
upvoted 0 times
...
Basilia
10 months ago
Activity G does require 3 weeks, not 4.
upvoted 0 times
...
...
Helaine
11 months ago
Joke's on them, I'm just gonna guess C and hope for the best. No float? Easy peasy!
upvoted 0 times
Karl
10 months ago
Fingers crossed for option C then!
upvoted 0 times
...
Luis
10 months ago
Yeah, I agree. Let's hope for the best!
upvoted 0 times
...
Yolando
11 months ago
I think I'll go with option C too. No float available sounds simple enough.
upvoted 0 times
...
...
Leota
11 months ago
Okay, let me grab my calculator and get to work. This is gonna take some serious number crunching.
upvoted 0 times
...
Magdalene
11 months ago
I bet the answer is D. Eight weeks of float for Activity A? Sign me up!
upvoted 0 times
Louvenia
10 months ago
I agree with you, I also think the answer is A.
upvoted 0 times
...
Luisa
10 months ago
I think the answer is A. Activity A has two weeks float and activity F has one week.
upvoted 0 times
...
...
Nichelle
11 months ago
Hmm, this project schedule seems a bit complicated. I better break it down step-by-step to find the float.
upvoted 0 times
...
Selma
12 months ago
But what about Activity A? Doesn't it have some float available?
upvoted 0 times
...
Cletus
12 months ago
I agree with Annice, it seems like all activities are on a tight schedule.
upvoted 0 times
...
Annice
12 months ago
I think there is no float available in the project.