BCS Exam ISEB-PM1 Topic 6 Question 94 Discussion

Actual exam question for BCS's ISEB-PM1 exam
Question #: 94
Topic #: 6
[All ISEB-PM1 Questions]

A project has seven activities: A, B, C, D, E, F, and G. Activities A, B, and D can start anytime. Activity A takes 3 weeks, Activity B takes 5 weeks, and Activity D takes 11 weeks. Activities A and B must be completed before Activity C can start. Activity C requires 6 weeks to complete. Activities B, C, and D must be completed before Activity E can start. Activity E requires 2 weeks. Activity F takes 4 weeks and can start as soon as Activity C is completed. Activity E must be completed before Activity G starts. Activity G requires 3 weeks. Activities F and G must be completed for the project to be completed. Which activities have float available?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Salley
28 days ago
Wait, did they say Activity G requires 3 weeks? I thought it was a trick question and the answer was 4 weeks. Dang it!
upvoted 0 times
Basilia
16 days ago
Activity G does require 3 weeks, not 4.
upvoted 0 times
...
...
Helaine
1 months ago
Joke's on them, I'm just gonna guess C and hope for the best. No float? Easy peasy!
upvoted 0 times
Karl
13 days ago
Fingers crossed for option C then!
upvoted 0 times
...
Luis
21 days ago
Yeah, I agree. Let's hope for the best!
upvoted 0 times
...
Yolando
26 days ago
I think I'll go with option C too. No float available sounds simple enough.
upvoted 0 times
...
...
Leota
1 months ago
Okay, let me grab my calculator and get to work. This is gonna take some serious number crunching.
upvoted 0 times
...
Magdalene
2 months ago
I bet the answer is D. Eight weeks of float for Activity A? Sign me up!
upvoted 0 times
Louvenia
16 days ago
I agree with you, I also think the answer is A.
upvoted 0 times
...
Luisa
18 days ago
I think the answer is A. Activity A has two weeks float and activity F has one week.
upvoted 0 times
...
...
Nichelle
2 months ago
Hmm, this project schedule seems a bit complicated. I better break it down step-by-step to find the float.
upvoted 0 times
...
Selma
2 months ago
But what about Activity A? Doesn't it have some float available?
upvoted 0 times
...
Cletus
2 months ago
I agree with Annice, it seems like all activities are on a tight schedule.
upvoted 0 times
...
Annice
2 months ago
I think there is no float available in the project.
upvoted 0 times
...

Save Cancel