BCS ISEB-PM1 Exam - Topic 4 Question 117 Discussion

A project manager and team from a firm that designs railroad equipment are tasked to design a machine to load stone onto railroad cars. The design allows for two percent spillage, amounting to over two tons of spilled rock per day. In which of the following does the project manager document quality control, quality assurance, and quality improvements for this project?
A) Quality management plan
B) Quality policy
C) Control charts
D) Project management plan

BCS ISEB-PM1 Exam - Topic 4 Question 117 Discussion

Actual exam question for BCS's ISEB-PM1 exam
Question #: 117
Topic #: 4
[All ISEB-PM1 Questions]

A project manager and team from a firm that designs railroad equipment are tasked to design a machine to load stone onto railroad cars. The design allows for two percent spillage, amounting to over two tons of spilled rock per day. In which of the following does the project manager document quality control, quality assurance, and quality improvements for this project?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

0/2000 characters
Salley
3 days ago
A) is the best choice, but I wonder if they’ll actually stick to it.
upvoted 0 times
...
Simona
8 days ago
I disagree, it’s not just about the plan, quality policy matters too!
upvoted 0 times
...
Louann
13 days ago
Wait, two tons of spillage? That's a lot! How is that acceptable?
upvoted 0 times
...
Rory
19 days ago
I think it could also be D) Project management plan. They overlap a bit.
upvoted 0 times
...
Nichelle
24 days ago
Definitely A) Quality management plan. That's where all the details go.
upvoted 0 times
...
Josue
29 days ago
I’m a bit confused; I thought the quality policy was important too, but it seems more about the overall approach rather than specific documentation.
upvoted 0 times
...
Laura
1 month ago
The project management plan seems like a broader document that might include quality aspects, but I feel like the quality management plan is more specific.
upvoted 0 times
...
Felton
1 month ago
I remember a practice question that mentioned control charts, but I don't think that's the right answer for documenting overall quality management.
upvoted 0 times
...
Avery
1 month ago
I think the quality management plan is where all the quality control and assurance details would be documented, but I'm not entirely sure.
upvoted 0 times
...