Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

BCS Exam ISEB-PM1 Topic 2 Question 99 Discussion

Actual exam question for BCS's ISEB-PM1 exam
Question #: 99
Topic #: 2
[All ISEB-PM1 Questions]

Given the following estimates: Optimistic 3 days, Pessimistic 9 days, and most likely

6 days, what is the PERT weighted average?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Clare
4 days ago
I disagree, I believe the answer is A) 6.1.
upvoted 0 times
...
Hermila
4 days ago
Hmm, let's see... Optimistic 3 days, Pessimistic 9 days, and most likely 6 days. Sounds like a job for the PERT formula! I'm going with B) 6.3.
upvoted 0 times
...
Stephaine
19 days ago
I think the answer is B) 6.3.
upvoted 0 times
...

Save Cancel