BCS ISEB-PM1 Exam - Topic 2 Question 26 Discussion

Actual exam question for BCS's ISEB-PM1 exam
Question #: 26
Topic #: 2
[All ISEB-PM1 Questions]

The project manager decides to conduct a meeting with the team and management after a new risk has been identified. After the meeting, the decision is to allow the risk to occur. This is an example of which type of risk response strategy?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

0/2000 characters
Nikita
4 months ago
Sounds like a bad idea to me, should've mitigated it!
upvoted 0 times
...
Orville
4 months ago
Wait, are we really okay with just letting it happen?
upvoted 0 times
...
Yolande
4 months ago
Totally agree, it's B - Accept.
upvoted 0 times
...
Kenneth
4 months ago
I think it's risky to just accept it like that.
upvoted 0 times
...
Elsa
5 months ago
That's definitely an acceptance strategy.
upvoted 0 times
...
Luis
5 months ago
I'm pretty confident that Organization-Wide Defaults is not a method for controlling record-level access. That's more about setting default access levels across the org.
upvoted 0 times
...
Janine
5 months ago
Hmm, this looks like a tricky one. I'll need to think through the earned value metrics carefully to determine where the project is struggling.
upvoted 0 times
...

Save Cancel