Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

BCS ISEB-PM1 Exam - Topic 12 Question 111 Discussion

A project manager discovers that two team members discussed what was needed to complete a work package on the project and made many changes to the project scope. The work package is now completed and the team members are planning to go on to the next work package. In looking at what was done, the project manager determines that the work does NOT meet the requirements of the project. What is the BEST course of action for the project manager?
B) Refuse the submittal of the work package.
A) Add another work package, formatted with the correct scope, to the project.
C) Have the team begin the work package again and include the incident in their performance reviews.
D) Ask the team member's manager to assign different people to the work package.

BCS ISEB-PM1 Exam - Topic 12 Question 111 Discussion

Actual exam question for BCS's ISEB-PM1 exam
Question #: 111
Topic #: 12
[All ISEB-PM1 Questions]

A project manager discovers that two team members discussed what was needed to complete a work package on the project and made many changes to the project scope. The work package is now completed and the team members are planning to go on to the next work package. In looking at what was done, the project manager determines that the work does NOT meet the requirements of the project. What is the BEST course of action for the project manager?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

0/2000 characters
Rosamond
2 days ago
This is tricky. I think B is the best choice.
upvoted 0 times
...
Carmela
7 days ago
Adding another work package seems like a band-aid solution.
upvoted 0 times
...
Janessa
12 days ago
Starting over with option C sounds fair, but tough on the team.
upvoted 0 times
...
Telma
17 days ago
Wait, how did they mess up the scope so badly?
upvoted 0 times
...
Leonardo
22 days ago
Totally agree, refusing the submittal makes sense!
upvoted 0 times
...
Alisha
27 days ago
I think option B is the best choice. Can't accept work that doesn't meet requirements.
upvoted 0 times
...
Juan
1 month ago
I feel like asking for different team members might not solve the underlying issue. It’s more about communication and clarity in the project scope, right?
upvoted 0 times
...
Brandee
3 months ago
This reminds me of a similar practice question where we had to address scope creep. I think adding another work package could just complicate things more.
upvoted 0 times
...
Herman
3 months ago
I’m not sure if refusing the submittal is the best move. Maybe starting over would be more effective, but it feels harsh to include it in performance reviews.
upvoted 0 times
...
Maricela
3 months ago
I remember discussing the importance of scope management in class. It seems like the team really went off track here.
upvoted 0 times
...

Save Cancel