Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

BCS ISEB-PM1 Exam - Topic 12 Question 111 Discussion

Actual exam question for BCS's ISEB-PM1 exam
Question #: 111
Topic #: 12
[All ISEB-PM1 Questions]

A project manager discovers that two team members discussed what was needed to complete a work package on the project and made many changes to the project scope. The work package is now completed and the team members are planning to go on to the next work package. In looking at what was done, the project manager determines that the work does NOT meet the requirements of the project. What is the BEST course of action for the project manager?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

0/2000 characters

Currently there are no comments in this discussion, be the first to comment!


Save Cancel