A project manager discovers that two team members discussed what was needed to complete a work package on the project and made many changes to the project scope. The work package is now completed and the team members are planning to go on to the next work package. In looking at what was done, the project manager determines that the work does NOT meet the requirements of the project. What is the BEST course of action for the project manager?
Ashanti
1 hour agoRosamond
5 days agoRebeca
10 days agoAshanti
16 days agoRosamond
21 days agoRebeca
26 days agoAshanti
1 month agoRosamond
1 month agoRebeca
1 month agoRosamond
2 months agoCarmela
2 months agoJanessa
2 months agoTelma
2 months agoLeonardo
2 months agoAlisha
2 months agoJuan
3 months agoBrandee
4 months agoHerman
4 months agoMaricela
4 months ago