Which of the following is an input to Develop Human Resource Plan?

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

Bernardine
3 days ago
I think the answer is A) Team performance assessment.
upvoted 0 times
...
Tammara
4 days ago
I think the correct answer is C) Staffing management plan. That's a key input to the Develop Human Resource Plan process.
upvoted 0 times
...