BCS Exam ISEB-PM1 Topic 10 Question 72 Discussion

Actual exam question for BCS's ISEB-PM1 exam
Question #: 72
Topic #: 10
[All ISEB-PM1 Questions]

Based on the chart, while completing the project, a team member tells you that the team forgot something during planning. Activity F needs the results of activity E before it can begin. Taking this new dependency into account, what would be the effect on the project?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Madalyn
19 days ago
Ugh, these exam questions are like a bad joke sometimes. But I've got to go with D - the new dependency is gonna throw a wrench in the works.
upvoted 0 times
Marti
2 days ago
A) It would increase the critical path.
upvoted 0 times
...
...
Terrilyn
1 months ago
Haha, classic team oversight. I bet they were too busy playing ping-pong in the break room to notice this little detail. D is the right answer, no doubt.
upvoted 0 times
Lindsey
17 days ago
User 2: A) It would increase the critical path.
upvoted 0 times
...
Ligia
27 days ago
User 1: Haha, classic team oversight. I bet they were too busy playing ping-pong in the break room to notice this little detail.
upvoted 0 times
...
...
Jamie
2 months ago
Oh, man, this is why I hate it when teams forget to plan properly. Definitely going with D, it's going to delay F for sure.
upvoted 0 times
Nobuko
10 days ago
Yeah, it's frustrating when things like this happen. Delaying activity F is definitely a possibility.
upvoted 0 times
...
Mariko
1 months ago
I agree, forgetting things during planning always causes delays.
upvoted 0 times
...
...
Sherill
2 months ago
Hmm, this is a tricky one. I think the answer is D, it would delay activity F. The new dependency means F can't start until E is completed, so the timeline will be impacted.
upvoted 0 times
...
Malcom
2 months ago
But wouldn't it also increase the critical path if there's a new dependency?
upvoted 0 times
...
Jolene
2 months ago
I agree with King, if activity F needs the results of activity E, then it would definitely delay activity F.
upvoted 0 times
...
King
2 months ago
I think the effect would be that it would delay activity F.
upvoted 0 times
...
Marylyn
2 months ago
But wouldn't it also increase the critical path since there is a new dependency?
upvoted 0 times
...
Jaime
2 months ago
I agree with Earleen, if activity F needs the results of activity E, it would definitely cause a delay.
upvoted 0 times
...
Earleen
2 months ago
I think the effect would be that it would delay activity F.