BCS ISEB-PM1 Exam - Topic 10 Question 72 Discussion

Actual exam question for BCS's ISEB-PM1 exam
Question #: 72
Topic #: 10
[All ISEB-PM1 Questions]

Based on the chart, while completing the project, a team member tells you that the team forgot something during planning. Activity F needs the results of activity E before it can begin. Taking this new dependency into account, what would be the effect on the project?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

0/2000 characters
Jesusita
4 months ago
Increased critical path is a real possibility here.
upvoted 0 times
...
Carissa
4 months ago
Yeah, more dependencies mean more complexity.
upvoted 0 times
...
Ming
4 months ago
Wait, how can it not affect the timeline?
upvoted 0 times
...
Louisa
5 months ago
Totally agree, we need E done first!
upvoted 0 times
...
Cherry
5 months ago
It would delay activity F.
upvoted 0 times
...
Zona
5 months ago
I thought dependencies just complicated things, but I can't recall if it always leads to delays or not.
upvoted 0 times
...
Jeff
5 months ago
This reminds me of a practice question where a new dependency changed the critical path. I think it could increase it.
upvoted 0 times
...
Tammara
5 months ago
I'm not entirely sure, but I feel like if F can't start until E is done, it could definitely impact the timeline.
upvoted 0 times
...
Ligia
6 months ago
I remember something about dependencies affecting the schedule, so I think it might delay activity F.
upvoted 0 times
...
Svetlana
6 months ago
Easy peasy! The new dependency for activity F will increase the critical path, since it has to wait for activity E to finish first. Simple as that.
upvoted 0 times
...
Viva
6 months ago
Okay, I think I've got this. The new dependency for activity F means it can't start until the results from activity E are available. That's going to delay activity F and push out the critical path.
upvoted 0 times
...
Glory
6 months ago
Ugh, I'm a bit confused by this one. I'll need to re-read the question and really think through how the new dependency would affect the project timeline.
upvoted 0 times
...
Whitley
6 months ago
Hmm, this seems straightforward. I'll need to carefully analyze the dependencies and how the new dependency for activity F would impact the critical path.
upvoted 0 times
...
Marguerita
6 months ago
Based on the details provided, I think the best approach would be to focus on the backend testing and use the programmed scripts to simulate the client behavior. That way we can really isolate any issues with the application itself, rather than getting bogged down in the user behavior and device variability.
upvoted 0 times
...
Tawna
6 months ago
Hmm, this looks like a tricky one. I'll need to think through the key components of a FlexPod design with ONTAP 9.7 and logical data separation.
upvoted 0 times
...
Madalyn
10 months ago
Ugh, these exam questions are like a bad joke sometimes. But I've got to go with D - the new dependency is gonna throw a wrench in the works.
upvoted 0 times
Chanel
9 months ago
D) It would delay activity F.
upvoted 0 times
...
Marguerita
10 months ago
B) Communication would be more complex.
upvoted 0 times
...
Marti
10 months ago
A) It would increase the critical path.
upvoted 0 times
...
...
Terrilyn
11 months ago
Haha, classic team oversight. I bet they were too busy playing ping-pong in the break room to notice this little detail. D is the right answer, no doubt.
upvoted 0 times
Earlean
10 months ago
User 4: D) It would delay activity F.
upvoted 0 times
...
Fidelia
10 months ago
User 3: B) Communication would be more complex.
upvoted 0 times
...
Lindsey
10 months ago
User 2: A) It would increase the critical path.
upvoted 0 times
...
Ligia
11 months ago
User 1: Haha, classic team oversight. I bet they were too busy playing ping-pong in the break room to notice this little detail.
upvoted 0 times
...
...
Jamie
11 months ago
Oh, man, this is why I hate it when teams forget to plan properly. Definitely going with D, it's going to delay F for sure.
upvoted 0 times
Nobuko
10 months ago
Yeah, it's frustrating when things like this happen. Delaying activity F is definitely a possibility.
upvoted 0 times
...
Mariko
11 months ago
I agree, forgetting things during planning always causes delays.
upvoted 0 times
...
...
Sherill
11 months ago
Hmm, this is a tricky one. I think the answer is D, it would delay activity F. The new dependency means F can't start until E is completed, so the timeline will be impacted.
upvoted 0 times
...
Malcom
11 months ago
But wouldn't it also increase the critical path if there's a new dependency?
upvoted 0 times
...
Jolene
12 months ago
I agree with King, if activity F needs the results of activity E, then it would definitely delay activity F.
upvoted 0 times
...
King
12 months ago
I think the effect would be that it would delay activity F.
upvoted 0 times
...
Marylyn
12 months ago
But wouldn't it also increase the critical path since there is a new dependency?
upvoted 0 times
...
Jaime
12 months ago
I agree with Earleen, if activity F needs the results of activity E, it would definitely cause a delay.
upvoted 0 times
...
Earleen
12 months ago
I think the effect would be that it would delay activity F.
upvoted 0 times
...

Save Cancel