BCS ISEB-PM1 Exam - Topic 10 Question 39 Discussion

Posted by Taryn on Jun 14, 2022 at 01:31 AM

Which of the following is a schedule network analysis technique that takes limited resources into account?

Suggested Answer: B

Get Premium ISEB-PM1 Questions as Interactive Web-Based Practice Test or PDF Real Exam Format Detailed Explanations Instant Access Get Your Practice Test
13 comments · newest first
YV
Yvonne 11 months ago
Really? I’m surprised that’s the answer. I need to look into this more.
ME
Merilyn 11 months ago
Yup, Critical chain is key for balancing resources!
BI
Billi 12 months ago
Wait, I thought the Critical path method was the go-to for scheduling?
DO
Dorothy 12 months ago
Totally agree, it's all about resource management!
FR
France 12 months ago
The Critical chain method is the one that considers limited resources.
CA
Carmelina 1 year ago
I’m leaning towards the Critical chain method too, but I wonder if Lead and lag adjustment could also be relevant in some way.
RE
Refugia 1 year ago
I feel like Network reserve analysis was mentioned in our notes, but I can't recall if it specifically relates to limited resources.
ST
Stefania 1 year ago
I remember practicing a question about this, and I think the Critical path method doesn't consider limited resources, so it can't be the right answer.
AM
Amber 1 year ago
I think the answer might be the Critical chain method, but I'm not entirely sure. It seems to focus on resource constraints.
AL
Alysa 1 year ago
I'm a bit confused by this question. The code doesn't seem to resemble any of the options provided. I'll need to take a closer look and try to identify any specific language features that might help me determine the correct answer.
FE
Felicitas 1 year ago
I feel like strong stakeholder communication is important, but is it really an expansion opportunity? I don't think so.
LI
Lindsey 1 year ago
I remember calculating overhead absorption rates before, but I'm mixed up on how that applies directly to each type of toilet.
QU
Queenie 1 year ago
I think the highest priority should be assigned to the most recently created app layer, so maybe it's App Layer C?