BCS Exam ISEB-PM1 Topic 10 Question 24 Discussion

Actual exam question for BCS's ISEB-PM1 exam
Question #: 24
Topic #: 10
[All ISEB-PM1 Questions]

What tool or technique of Estimate Activity Durations uses parameters such as duration, budget, size, weight, and complexity from a previous, similar project as the basis for estimating the same parameter or measure for a future project?

Show Suggested Answer Hide Answer
Suggested Answer: B