Your team switched to using story points for estimation in the last 2months and their sprints are 2weeks long.
Which chart can definitely help you determine the average effort that the team can deliver during each sprint?
Suggested Answer: A
Get Premium ACP-620 Questions
as Interactive Web-Based Practice Test or PDF
Real Exam Format
Detailed Explanations
Instant Access
Get Your Practice Test
The Velocity Chart shows the amount of story points completed in each sprint, allowing you to determine the average effort the team can deliver. It's specifically designed to track estimation units like story points across completed sprints.
18 comments · newest first
JO
Jordan
2 months ago
I’m convinced, Velocity Chart it is!
NI
Nicholle
2 months ago
Right! It’s all about improving our estimates.
OR
Orville
2 months ago
Plus, it helps with future sprint planning.
JO
Jordan
2 months ago
I see your point. Velocity Chart gives a clearer picture.
NI
Nicholle
2 months ago
Exactly! We need to see our capacity over time.
OR
Orville
2 months ago
True, but it doesn’t show average effort like the Velocity Chart does.
JO
Jordan
3 months ago
But what about the Burndown Chart? It tracks progress too.
NI
Nicholle
3 months ago
Agreed, it shows how much work we complete each sprint.
OR
Orville
3 months ago
I think the Velocity Chart is the best choice.
LU
Lucille
3 months ago
Not sure if we have enough data yet for a solid average.
GI
Gilma
3 months ago
Yeah, Velocity Chart is the way to go!
MA
Mauricio
4 months ago
Wait, can the Cumulative Flow Diagram help with that?
NA
Nan
4 months ago
I thought the Burndown Chart would work too.
LO
Lottie
4 months ago
Definitely the Velocity Chart!
VA
Van
4 months ago
I practiced with a similar question, and I believe the Velocity Chart is definitely the right choice for measuring average effort over sprints.
JA
Jamie
4 months ago
I feel like the Cumulative Flow Diagram might be useful, but it seems more about workflow than just effort per sprint.
MA
Marjory
4 months ago
I'm not entirely sure, but I remember something about the Burndown Chart tracking work left to do. Does it help with average effort too?
RU
Rupert
5 months ago
I think the Velocity Chart is the one we learned about that shows how many story points the team completes in each sprint.