Atlassian ACP-620 Exam - Topic 1 Question 18 Discussion

Actual exam question for Atlassian's ACP-620 exam
Question #: 18
Topic #: 1
[All ACP-620 Questions]

Your team switched to using story points for estimation in the last 2months and their sprints are 2weeks long.

Which chart can definitely help you determine the average effort that the team can deliver during each sprint?

Show Suggested Answer Hide Answer
Suggested Answer: A

The Velocity Chart shows the amount of story points completed in each sprint, allowing you to determine the average effort the team can deliver. It's specifically designed to track estimation units like story points across completed sprints.


Contribute your Thoughts:

0/2000 characters
Avery
3 days ago
I think the Velocity Chart would be the right choice since it shows how many story points the team completes each sprint.