New Year Sale 2026! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

Atlassian ACP-620 Exam - Topic 3 Question 14 Discussion

Actual exam question for Atlassian's ACP-620 exam
Question #: 14
Topic #: 3
[All ACP-620 Questions]

Your team switched to using story points for estimation in the last 2months and their sprints are 2weeks long.

Which chart can definitely help you determine the average effort that the team can deliver during each sprint?

Show Suggested Answer Hide Answer
Suggested Answer: A

The Velocity Chart shows the amount of story points completed in each sprint, allowing you to determine the average effort the team can deliver. It's specifically designed to track estimation units like story points across completed sprints.


Contribute your Thoughts:

0/2000 characters
Janine
9 hours ago
Totally agree, it's all about tracking velocity.
upvoted 0 times
...
Arlette
6 days ago
A) Velocity Chart is the one!
upvoted 0 times
...
Kenneth
11 days ago
Burndown Chart, it's the one that makes me feel like I'm in a spy movie.
upvoted 0 times
...
Huey
16 days ago
Velocity Chart, because who doesn't love a good old-fashioned bar chart?
upvoted 0 times
...
Art
21 days ago
Cumulative Flow Diagram, that's the one that really shows the team's progress.
upvoted 0 times
...
Keshia
26 days ago
Burndown Chart is the answer, it's the classic agile chart.
upvoted 0 times
...
Tesha
1 month ago
Burnup Chart is the way to go, it shows the progress over time.
upvoted 0 times
...
Verlene
1 month ago
I feel like the Cumulative Flow Diagram might show progress, but it doesn't really focus on average effort like the Velocity Chart does.
upvoted 0 times
...
Portia
1 month ago
I practiced a similar question, and I believe the Velocity Chart is definitely the one that reflects the team's capacity over time.
upvoted 0 times
...
Thaddeus
2 months ago
I'm not entirely sure, but I remember something about the Burndown Chart tracking work left to do. Would that help with average effort?
upvoted 0 times
...
Clay
2 months ago
I think the Velocity Chart would be the right choice since it shows how many story points the team completes in each sprint.
upvoted 0 times
...
Jacinta
2 months ago
Okay, let me think this through. Since the team is using story points and 2-week sprints, the velocity chart is probably the best way to see their average delivery per sprint.
upvoted 0 times
...
Pete
2 months ago
Hmm, I'm not sure. The cumulative flow diagram might also give me a good sense of the team's average sprint effort.
upvoted 0 times
...
Cecily
2 months ago
Velocity Chart for sure, that's the way to go!
upvoted 0 times
...
Delisa
2 months ago
I think the Velocity Chart is the best choice.
upvoted 0 times
...
Daron
3 months ago
The velocity chart is definitely the way to go. That will show me the team's consistent delivery over the past sprints.
upvoted 0 times
...
Kaitlyn
3 months ago
Cumulative Flow Diagram is also useful, but not for this.
upvoted 0 times
...
Stephania
3 months ago
I'm a bit confused - I thought the burndown chart would be the best option to see the team's average sprint delivery.
upvoted 0 times
...
Delsie
3 months ago
The velocity chart seems like the obvious choice here since it tracks the team's actual delivery over time.
upvoted 0 times
...

Save Cancel