ASQ CSSBB Exam - Topic 8 Question 15 Discussion

A team wants to make a schedule for a project showing which tasks must be done sequentially and which may be done simultaneously. Which tool is most appropriate?
E) activity network diagram
A) matrix diagram
B) cause and effect diagram
C) process decision program chart
D) affinity diagram
F) tree diagram
G) prioritization matrix
H) matrix diagram
I) interrelationship digraph

ASQ CSSBB Exam - Topic 8 Question 15 Discussion

Actual exam question for ASQ's CSSBB exam
Question #: 15
Topic #: 8
[All CSSBB Questions]

A team wants to make a schedule for a project showing which tasks must be done sequentially and which may be done simultaneously. Which tool is most appropriate?

Show Suggested Answer Hide Answer
Suggested Answer: E

Contribute your Thoughts:

0/2000 characters
Sherell
8 months ago
I thought a cause and effect diagram was for something else?
upvoted 0 times
...
Justine
9 months ago
Totally agree, activity network is the way to go!
upvoted 0 times
...
Cathern
9 months ago
Wait, can you really do tasks simultaneously with that?
upvoted 0 times
...
Gerald
9 months ago
I think a matrix diagram could work too.
upvoted 0 times
...
Quinn
9 months ago
Activity network diagram is the best for this!