Which of the following tools can be used to determine the time needed to install a new computer system?

Suggested Answer: A

An Activity Network Diagram, also known as a project network diagram or a PERT (Program Evaluation Review Technique) chart, is a tool used in project management to schedule, organize, and coordinate tasks within a project. It helps in determining the time required to complete a project by identifying the sequence of activities, dependencies, and the critical path, which is essential for determining the total time needed for the installation of a new computer system.


'Project Management: A Systems Approach to Planning, Scheduling, and Controlling' by Harold Kerzner.

PMI (Project Management Institute) PMBOK Guide (Project Management Body of Knowledge)

Get Premium CQE Questions as Interactive Web-Based Practice Test or PDF Real Exam Format Detailed Explanations Instant Access Get Your Practice Test
13 comments · newest first
PR
Precious 10 months ago
I thought D was useful for prioritizing, not timing.
IL
Ilona 10 months ago
Not so sure about that, B could also help with organizing tasks.
NA
Nada 10 months ago
I agree, A is the best choice here!
SO
Sophia 10 months ago
Wait, can a cause and effect diagram really help with installation time?
JE
Jess 11 months ago
Definitely A, the activity network diagram is key for timing.
DA
Dawne 11 months ago
The prioritization matrix seems off for this question; I thought it was more for ranking tasks rather than estimating time.
TI
Tiara 11 months ago
I feel like I've seen a similar question before, and I think the cause and effect diagram was not the right tool for timing estimates.
KE
Keshia 11 months ago
I'm not entirely sure, but I remember the affinity diagram is more about organizing ideas rather than timing.
CA
Carin 12 months ago
I think the activity network diagram is the right choice since it helps visualize tasks and their dependencies.
BR
Britt 12 months ago
I'm a bit confused by this question. I'm not super familiar with all these different diagrams and tools. I'll have to guess on this one and hope for the best.
EL
Elfriede 12 months ago
Okay, let me think this through step-by-step. An activity network diagram is used to map out the sequence of tasks and dependencies in a project, which would help determine the overall timeline. The other options don't seem as directly relevant to estimating installation time. I'll go with A.
AL
Alana 1 year ago
Hmm, I'm not totally sure about this one. I think the activity network diagram might be the best choice, but I'm not 100% confident. I'll have to think it through carefully.
YU
Yuriko 1 year ago
This looks like a straightforward question. I'd go with option A, the activity network diagram, since that's a common tool used to plan and schedule project timelines.