In which step of the Continuous Change Management Cycle should change actions be broken into smaller tasks?
Comprehensive and Detailed In-Depth
The Continuous Change Cycle (Discovery, Ideas, Prioritization, Action) in APMG is iterative. Breaking actions into tasks occurs in Action, where plans are executed. Let's analyze:
* Discovery: Assesses needs (e.g., low morale). No tasks yet---just insights.
* Ideas: Generates solutions (e.g., better communication). Still conceptual.
* Prioritization: Ranks ideas (e.g., training first). Defines what, not how.
* Action: Correct. Implements plans, breaking them into tasks (e.g., ''schedule training'' vs. ''launch campaign''). APMG stresses manageability here.
* Example: A morale boost via training is split into actionable steps (e.g., book trainer, set dates) in Action.