Answer the following question about spending objectives for the Pittville project.The following questions include only true statements about the Pittville project, but only 1 statement is an appropriately definedSMART spending objective for the stated outcome.Which is an appropriately defined SMART spending objective for increased 16-18 year-old learners participation?
A) To increase the rate of 16-18-year-olds in education and training by at least 15% within three years.
B) To offer a broader range of education courses for 16-18-year-olds.
C) To accommodate a further 80 full time learners within thePittville University existing facility.
D) To absorb 11-16 year-old pupils from Pittville High into the other schools if all further education units were moved to a new campus.