Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

APMG-International Exam AgilePM-Practitioner Topic 2 Question 18 Discussion

Actual exam question for APMG-International's AgilePM-Practitioner exam
Question #: 18
Topic #: 2
[All AgilePM-Practitioner Questions]

How should the Project Manager encourage the contractors to turn up on time?

Show Suggested Answer Hide Answer
Suggested Answer: B, C

Contribute your Thoughts:

Noemi
19 days ago
Option B sounds good, but why not just have the project manager lead the stand-up with the contractors? That way, they can address any issues directly.
upvoted 0 times
...
Louis
21 days ago
Haha, Option A is like the project manager saying, 'Hey, contractors, we don't trust you, so we're going to fine you if you're late!' Not a great way to foster cooperation.
upvoted 0 times
...
James
23 days ago
Placing a penalty clause (Option A) might work, but it could also create an adversarial environment. I think Option C is the better choice here.
upvoted 0 times
Elke
10 hours ago
I agree, Option C would help build a better relationship with the contractors.
upvoted 0 times
...
...
Charlene
27 days ago
I'd go with Option D. Holding a separate daily stand-up meeting for contractors can help keep them accountable and on schedule.
upvoted 0 times
Arthur
20 days ago
Option D sounds like a good idea. It can help set the tone for the day.
upvoted 0 times
...
...
Willis
1 months ago
Option C seems the most reasonable approach to address the issue. Open communication and trust-building are key for effective collaboration with contractors.
upvoted 0 times
...
Mitsue
2 months ago
I agree with Charolette, option D would help improve communication and coordination among the contractors.
upvoted 0 times
...
Charolette
2 months ago
I disagree, I believe option D would be more effective as it provides a dedicated time for the contractors to discuss their schedules.
upvoted 0 times
...
Tony
2 months ago
I think option A is the best way to ensure contractors arrive on time.
upvoted 0 times
...

Save Cancel