Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

Adobe AD0-E911 Exam - Topic 2 Question 9 Discussion

The last 5 tasks in a project need to happen within 10 days of the end of the project.Which Task Constraint should the project manager use to configure this timeline without setting specific dates?
C) As Late As Possible
A) Start No Later Than
B) Must Start On

Adobe AD0-E911 Exam - Topic 2 Question 9 Discussion

Actual exam question for Adobe's AD0-E911 exam
Question #: 9
Topic #: 2
[All AD0-E911 Questions]

The last 5 tasks in a project need to happen within 10 days of the end of the project.

Which Task Constraint should the project manager use to configure this timeline without setting specific dates?

Show Suggested Answer Hide Answer
Suggested Answer: C

In Workfront, the 'As Late As Possible' task constraint ensures that tasks are scheduled as close to the project's end date as possible. This is useful when specific start dates are not necessary, but tasks need to happen near the end of the project timeline. This constraint allows for flexibility while still ensuring that the tasks are completed within the required time frame.


Contribute your Thoughts:

0/2000 characters
Tawny
4 days ago
"Must Start On" feels too rigid. We need some leeway for changes.
upvoted 0 times
...
Katy
9 days ago
I disagree. "Start No Later Than" ensures we don’t miss deadlines.
upvoted 0 times
...
Germaine
14 days ago
I think "As Late As Possible" is the best choice. It gives flexibility.
upvoted 0 times
...
Nobuko
20 days ago
Totally agree, Must Start On makes the most sense!
upvoted 0 times
...
Stevie
25 days ago
Wait, can you really do that without specific dates? Sounds tricky!
upvoted 0 times
...
Edgar
30 days ago
The tasks need to be done within 10 days, so timing is crucial.
upvoted 0 times
...
Trinidad
1 month ago
I think As Late As Possible could work too.
upvoted 0 times
...
Selma
1 month ago
Must Start On is the best choice here.
upvoted 0 times
...
Jacquelyne
2 months ago
I’m a bit confused, but I think C) As Late As Possible could work since it gives the team time to finish earlier tasks first.
upvoted 0 times
...
Demetra
2 months ago
I feel like I've seen a similar question before, and it was about managing deadlines without specific dates. Maybe it's A) Start No Later Than?
upvoted 0 times
...
Glory
2 months ago
I'm not entirely sure, but I remember something about "Must Start On" being too rigid for this scenario.
upvoted 0 times
...
Lucy
2 months ago
I think the answer might be C) As Late As Possible since it allows for flexibility in scheduling the last tasks.
upvoted 0 times
...

Save Cancel