The last 5 tasks in a project need to happen within 10 days of the end of the project.
Which Task Constraint should the project manager use to configure this timeline without setting specific dates?
Suggested Answer: C
Get Premium AD0-E911 Questions
as Interactive Web-Based Practice Test or PDF
Real Exam Format
Detailed Explanations
Instant Access
Get Your Practice Test
In Workfront, the 'As Late As Possible' task constraint ensures that tasks are scheduled as close to the project's end date as possible. This is useful when specific start dates are not necessary, but tasks need to happen near the end of the project timeline. This constraint allows for flexibility while still ensuring that the tasks are completed within the required time frame.
12 comments · newest first
TA
Tawny
2 months ago
"Must Start On" feels too rigid. We need some leeway for changes.
KA
Katy
2 months ago
I disagree. "Start No Later Than" ensures we don’t miss deadlines.
GE
Germaine
2 months ago
I think "As Late As Possible" is the best choice. It gives flexibility.
NO
Nobuko
2 months ago
Totally agree, Must Start On makes the most sense!
ST
Stevie
2 months ago
Wait, can you really do that without specific dates? Sounds tricky!
ED
Edgar
3 months ago
The tasks need to be done within 10 days, so timing is crucial.
TR
Trinidad
3 months ago
I think As Late As Possible could work too.
SE
Selma
3 months ago
Must Start On is the best choice here.
JA
Jacquelyne
3 months ago
I’m a bit confused, but I think C) As Late As Possible could work since it gives the team time to finish earlier tasks first.
DE
Demetra
3 months ago
I feel like I've seen a similar question before, and it was about managing deadlines without specific dates. Maybe it's A) Start No Later Than?
GL
Glory
3 months ago
I'm not entirely sure, but I remember something about "Must Start On" being too rigid for this scenario.
LU
Lucy
4 months ago
I think the answer might be C) As Late As Possible since it allows for flexibility in scheduling the last tasks.