A project manager is assigned to a new Workfront request. The request specifies that the management team's sign-off is needed before the project can begin.
What is the appropriate action for the project manager to take?
Suggested Answer: C
Get Premium AD0-E911 Questions
as Interactive Web-Based Practice Test or PDF
Real Exam Format
Detailed Explanations
Instant Access
Get Your Practice Test
In Workfront, approval processes are designed to handle scenarios where certain team members must give formal approval before work can proceed. In this case, the project manager should set up a customized approval process that routes the request through the necessary stakeholders (management team) for their sign-off. This ensures proper governance and tracking.