Which project Condition is set when the Progress Status of the project is Behind or At Risk?
In Adobe Workfront, when a project's progress status is marked as Behind or At Risk, the project condition is set to At Risk. This indicates that the project may not meet its deadline or performance metrics, signaling to the project team and stakeholders that corrective action may be necessary. The 'In Trouble' status is reserved for more severe cases, and 'Late' is generally used for tasks or projects that have passed their planned completion dates without being finished.
The At Risk status allows proactive intervention to address potential issues before they escalate into bigger problems.