Adobe AD0-E911 Exam - Topic 2 Question 13 Discussion

Posted by Julian on Sep 28, 2026 at 03:52 PM

Which project Condition is set when the Progress Status of the project is Behind or At Risk?

Suggested Answer: B

In Adobe Workfront, when a project's progress status is marked as Behind or At Risk, the project condition is set to At Risk. This indicates that the project may not meet its deadline or performance metrics, signaling to the project team and stakeholders that corrective action may be necessary. The 'In Trouble' status is reserved for more severe cases, and 'Late' is generally used for tasks or projects that have passed their planned completion dates without being finished.

The At Risk status allows proactive intervention to address potential issues before they escalate into bigger problems.


Get Premium AD0-E911 Questions as Interactive Web-Based Practice Test or PDF Real Exam Format Detailed Explanations Instant Access Get Your Practice Test
9 comments · newest first
ST
Stephaine 3 days ago
The answer is A) Late, no doubt about it.
AN
Andra 8 days ago
I disagree, it should be A) Late for sure.
AL
Alica 14 days ago
Wait, is there a C) In Trouble option? Sounds dramatic!
FR
Francis 19 days ago
I think it's B) At Risk.
AM
Amie 24 days ago
It's definitely A) Late.
RO
Rory 29 days ago
I feel like "At Risk" is the most appropriate choice based on what we discussed in our last review session.
PA
Patti 1 month ago
"In Trouble" sounds familiar, but I don't recall it being a standard term we used.
VI
Vincenza 1 month ago
I remember practicing a question about project statuses, and "Late" was mentioned a lot. Could that be it?
IS
Isidra 1 month ago
I think the answer might be "At Risk," but I'm not entirely sure. We covered similar terms in class.