Adobe AD0-E911 Exam - Topic 1 Question 5 Discussion

The second task in a project should be completed within 48 hours and needs to begin 5 business days after the first task is completed.Which task settings should be configured to meet these requirements?
A) The task Duration should be set to 2 days. A predecessor with a Finish-Start Dependency Type should be added to the second task with a lag of 5 days.
B) Planned Hours should be set to 48 hours. A predecessor with a Finish-Start Dependency Type should be added to the first task with a lag of 5 days.
C) The task Duration should be set to 48 hours. A predecessor with a Start-Finish Dependency Type should be added to the second task with a lag of 5 days.

Adobe AD0-E911 Exam - Topic 1 Question 5 Discussion

Actual exam question for Adobe's AD0-E911 exam
Question #: 5
Topic #: 1
[All AD0-E911 Questions]

The second task in a project should be completed within 48 hours and needs to begin 5 business days after the first task is completed.

Which task settings should be configured to meet these requirements?

Show Suggested Answer Hide Answer
Suggested Answer: A

In Adobe Workfront, to configure tasks according to the requirement of the second task beginning 5 business days after the first task, you need to set the appropriate 'Duration' and use 'Finish-Start' dependencies. The task's duration is key to determining the time allowed for its completion. The 'Finish-Start' dependency ensures that the second task begins only after the first is finished, and a lag can be set to introduce a delay, such as 5 business days. Setting a 'Finish-Start' dependency with a lag allows for proper scheduling of tasks in sequence without overlapping.


Contribute your Thoughts:

0/2000 characters
Kayleigh
8 hours ago
Wait, isn't 48 hours just 2 days? Why the confusion?
upvoted 0 times
...
Shenika
6 days ago
I disagree, B seems more logical with the hours planned.
upvoted 0 times
...
Lura
11 days ago
Option A is correct. 2 days duration and 5 days lag makes sense.
upvoted 0 times
...
Tina
16 days ago
I think the task duration should be 48 hours, but I’m not sure if the lag should be added to the predecessor or the task itself. This is tricky!
upvoted 0 times
...
Annamae
2 months ago
I’m confused about the difference between Finish-Start and Start-Finish dependencies. I thought we always used Finish-Start for these types of tasks?
upvoted 0 times
...
Billy
2 months ago
I remember practicing a similar question where we had to set dependencies correctly. I feel like option A makes the most sense with the Finish-Start dependency.
upvoted 0 times
...
Nakita
2 months ago
I think the second task's duration should definitely be set to 2 days, but I'm not sure about the lag. Was it 5 business days or just 5 days?
upvoted 0 times
...