Adobe AD0-E911 Exam - Topic 1 Question 5 Discussion

Posted by Emerson on May 04, 2026 at 06:48 PM

The second task in a project should be completed within 48 hours and needs to begin 5 business days after the first task is completed.

Which task settings should be configured to meet these requirements?

Suggested Answer: A

In Adobe Workfront, to configure tasks according to the requirement of the second task beginning 5 business days after the first task, you need to set the appropriate 'Duration' and use 'Finish-Start' dependencies. The task's duration is key to determining the time allowed for its completion. The 'Finish-Start' dependency ensures that the second task begins only after the first is finished, and a lag can be set to introduce a delay, such as 5 business days. Setting a 'Finish-Start' dependency with a lag allows for proper scheduling of tasks in sequence without overlapping.


Get Premium AD0-E911 Questions as Interactive Web-Based Practice Test or PDF Real Exam Format Detailed Explanations Instant Access Get Your Practice Test
24 comments · newest first
TO
Tomoko 3 days ago
Why A?
LA
Lashunda 8 days ago
I think option A makes sense.
TO
Tomoko 13 days ago
This question is tricky!
RE
Reed 18 days ago
Agreed! A covers all bases.
ST
Stefania 23 days ago
A is the best choice overall.
TO
Tom 29 days ago
Yeah, C doesn't fit the 48-hour requirement well.
AL
Alaine 1 month ago
Option C seems off with that Start-Finish type.
RE
Reed 1 month ago
True, but it ensures the second starts after the first.
ST
Stefania 1 month ago
But B adds a lag to the first task, not the second.
TO
Tom 2 months ago
It focuses on planned hours, which is crucial.
TO
Tom 2 months ago
I prefer option B.
RE
Reed 2 months ago
It sets the duration right and adds the lag correctly.
AL
Alaine 2 months ago
Why A?
RE
Reed 2 months ago
I think option A makes sense.
AL
Alaine 3 months ago
This question is tricky!
WA
Walker 3 months ago
Not sure about C, Start-Finish doesn't fit the requirements at all.
PA
Pamella 3 months ago
A is definitely the way to go. Finish-Start with a lag is standard.
KA
Kayleigh 3 months ago
Wait, isn't 48 hours just 2 days? Why the confusion?
SH
Shenika 3 months ago
I disagree, B seems more logical with the hours planned.
LU
Lura 3 months ago
Option A is correct. 2 days duration and 5 days lag makes sense.
TI
Tina 4 months ago
I think the task duration should be 48 hours, but I’m not sure if the lag should be added to the predecessor or the task itself. This is tricky!
AN
Annamae 5 months ago
I’m confused about the difference between Finish-Start and Start-Finish dependencies. I thought we always used Finish-Start for these types of tasks?
BI
Billy 5 months ago
I remember practicing a similar question where we had to set dependencies correctly. I feel like option A makes the most sense with the Finish-Start dependency.
NA
Nakita 5 months ago
I think the second task's duration should definitely be set to 2 days, but I'm not sure about the lag. Was it 5 business days or just 5 days?