Given this information regarding a Task:
Planned Start Date: May 14
Actual Start Date: May 14
Planned Completion Date: May 20
Projected Completion Date: May 22
Percent Complete: 50%
Duration: 5 Days
Planned Hours: 8 Hours
Status: In Progress
If today's date were May 19, what would be the Task's progress status?
In Workfront, when the projected completion date exceeds the planned completion date and the task is only 50% complete by May 19, it is automatically flagged as 'At Risk.' This alerts the project manager that the task is not progressing according to the original plan, potentially causing delays in the project timeline.
Stephaine
8 hours agoLatia
6 days agoArgelia
11 days agoTracey
16 days agoElza
2 months agoRodolfo
2 months agoLeanora
2 months ago