Adobe AD0-E911 Exam - Topic 1 Question 4 Discussion

Actual exam question for Adobe's AD0-E911 exam
Question #: 4
Topic #: 1
[All AD0-E911 Questions]

Given this information regarding a Task:

Planned Start Date: May 14

Actual Start Date: May 14

Planned Completion Date: May 20

Projected Completion Date: May 22

Percent Complete: 50%

Duration: 5 Days

Planned Hours: 8 Hours

Status: In Progress

If today's date were May 19, what would be the Task's progress status?

Show Suggested Answer Hide Answer
Suggested Answer: C

In Workfront, when the projected completion date exceeds the planned completion date and the task is only 50% complete by May 19, it is automatically flagged as 'At Risk.' This alerts the project manager that the task is not progressing according to the original plan, potentially causing delays in the project timeline.