Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

Adobe AD0-E911 Exam - Topic 1 Question 4 Discussion

Given this information regarding a Task:Planned Start Date: May 14Actual Start Date: May 14Planned Completion Date: May 20Projected Completion Date: May 22Percent Complete: 50%Duration: 5 DaysPlanned Hours: 8 HoursStatus: In ProgressIf today's date were May 19, what would be the Task's progress status?
C) At Risk
A) Behind
B) On Time

Adobe AD0-E911 Exam - Topic 1 Question 4 Discussion

Actual exam question for Adobe's AD0-E911 exam
Question #: 4
Topic #: 1
[All AD0-E911 Questions]

Given this information regarding a Task:

Planned Start Date: May 14

Actual Start Date: May 14

Planned Completion Date: May 20

Projected Completion Date: May 22

Percent Complete: 50%

Duration: 5 Days

Planned Hours: 8 Hours

Status: In Progress

If today's date were May 19, what would be the Task's progress status?

Show Suggested Answer Hide Answer
Suggested Answer: C

In Workfront, when the projected completion date exceeds the planned completion date and the task is only 50% complete by May 19, it is automatically flagged as 'At Risk.' This alerts the project manager that the task is not progressing according to the original plan, potentially causing delays in the project timeline.


Contribute your Thoughts:

0/2000 characters
Stephaine
8 hours ago
I think it's still on time, just needs a push.
upvoted 0 times
...
Latia
6 days ago
Definitely behind schedule!
upvoted 0 times
...
Argelia
11 days ago
Task is 50% complete with a planned end date of May 20.
upvoted 0 times
...
Tracey
16 days ago
I feel like it could be considered at risk because the projected completion date is later than planned, but I'm not completely confident.
upvoted 0 times
...
Elza
2 months ago
This reminds me of a practice question where we had to determine if a task was on time based on percent complete. I think this one is behind.
upvoted 0 times
...
Rodolfo
2 months ago
I'm not entirely sure, but I remember something about how the projected completion date can indicate if a task is at risk.
upvoted 0 times
...
Leanora
2 months ago
I think the task is actually behind schedule since it should be 80% complete by May 19, but it's only at 50%.
upvoted 0 times
...

Save Cancel