New Year Sale 2026! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

Adobe AD0-E908 Exam - Topic 4 Question 11 Discussion

Actual exam question for Adobe's AD0-E908 exam
Question #: 11
Topic #: 4
[All AD0-E908 Questions]

A project team has configured a Kanban board with columns for backlog, in progress, on hold, and completed statuses. The project manager wishes to automatically archive cards that have been closed for longer than two weeks.

What should the project manager change in order to make this happen?

Show Suggested Answer Hide Answer
Suggested Answer: A

Identify the Requirement: The project manager wishes to automatically archive cards that have been closed for longer than two weeks on a Kanban board.

Understanding Card Falloff in Workfront: Workfront allows for the configuration of automatic archiving (card falloff) based on the time a card has been in a specific column. This is useful for maintaining a clean and organized Kanban board.

Steps to Configure Card Falloff:

Navigate to the Board: Go to the Kanban board where the columns for backlog, in progress, on hold, and completed statuses are set up.

Access Configuration: Click on 'Configure' to access the board settings.

Select Cards: In the configuration settings, go to the 'Cards' section.

Enable Card Falloff: Enable the option for card falloff and set it specifically for the 'Closed' column. Set the falloff duration to two weeks.

Implementation:

Apply Settings: Save the configuration changes to ensure that cards in the Closed column will automatically archive after two weeks.

Monitor: Regularly check to ensure that the card falloff is functioning as expected and that closed cards are being archived after the specified time.


Contribute your Thoughts:

0/2000 characters
Shannan
3 months ago
Agreed, B is straightforward and clear.
upvoted 0 times
...
Fletcher
3 months ago
Definitely not C, that sounds off.
upvoted 0 times
...
Bonita
3 months ago
Surprised this isn't a default feature!
upvoted 0 times
...
Jesus
4 months ago
I think A makes more sense, though.
upvoted 0 times
...
Dana
4 months ago
Option B is the right choice!
upvoted 0 times
...
Asuncion
4 months ago
I thought the archiving settings were more general, like in option C, but that doesn't seem to mention the two-week limit specifically.
upvoted 0 times
...
Earlean
4 months ago
I feel like option A sounds familiar, but I can't remember if "Card Falloff" is actually a feature we discussed.
upvoted 0 times
...
Detra
4 months ago
I remember something about configuring card settings, but I can't recall if it was under "Configure" or directly in the column settings.
upvoted 0 times
...
In
5 months ago
I think the answer might be B, but I'm not entirely sure if "Archive Limit" is the right term they used in our practice questions.
upvoted 0 times
...
Lovetta
5 months ago
I'm pretty confident that option B is the correct answer here. Setting the Archive Limit directly in the Closed column seems like the most straightforward way to achieve the desired behavior.
upvoted 0 times
...
Murray
5 months ago
Okay, let me think this through. I believe the key is that the project manager wants to automatically archive cards that have been closed for longer than two weeks. So the solution is probably going to involve setting some kind of time-based archive rule. I'm leaning towards option A, but I'll double-check the other choices.
upvoted 0 times
...
Glennis
5 months ago
This seems pretty straightforward. I think option B is the right answer - you just need to set the Archive Limit for the Closed column to two weeks.
upvoted 0 times
...
Rosita
5 months ago
Hmm, I'm a bit confused. Do I need to do something in the Configure settings, or is it just a matter of editing the Closed column? I want to make sure I get this right.
upvoted 0 times
...
Fredric
1 year ago
I think option C is the correct answer, the project manager should select Archive and set it for two weeks.
upvoted 0 times
...
Salley
1 year ago
Option B seems like the most straightforward solution. Can't go wrong with that one.
upvoted 0 times
Rusty
1 year ago
I think so too. It's important to keep things organized and automated.
upvoted 0 times
...
Torie
1 year ago
Yeah, I agree. It's simple and to the point.
upvoted 0 times
...
Lou
1 year ago
Option B seems like the most straightforward solution.
upvoted 0 times
...
...
Kandis
1 year ago
I disagree, I believe the project manager should select the Closed column and set the Archive Limit to two weeks.
upvoted 0 times
...
Elenor
1 year ago
Haha, I'm pretty sure the project manager is not going to select the three ellipses next to the board name. That's just ridiculous!
upvoted 0 times
...
Marcelle
1 year ago
I think the project manager should select Configure and enable a two week Card Falloff for the Closed column.
upvoted 0 times
...
Yolando
1 year ago
Hmm, I'm not sure. Option A sounds like it might be the correct one, but I'll double-check the details just to be sure.
upvoted 0 times
Francisca
1 year ago
Sounds good, let's make sure we have all the information before making a decision.
upvoted 0 times
...
Inocencia
1 year ago
I'm not sure, let's double-check the details before deciding.
upvoted 0 times
...
Venita
1 year ago
I agree, let's go with Option A.
upvoted 0 times
...
Laurel
1 year ago
I think Option A is the way to go.
upvoted 0 times
...
...
Ettie
1 year ago
Option B is clearly the way to go. Just set the Archive Limit for the Closed column, easy peasy!
upvoted 0 times
Lazaro
1 year ago
I agree, that sounds like the most straightforward solution.
upvoted 0 times
...
Elvis
1 year ago
Option B is clearly the way to go. Just set the Archive Limit for the Closed column, easy peasy!
upvoted 0 times
...
...

Save Cancel