New Year Sale 2026! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

Adobe AD0-E903 Exam - Topic 3 Question 26 Discussion

Actual exam question for Adobe's AD0-E903 exam
Question #: 26
Topic #: 3
[All AD0-E903 Questions]

Which date type on tasks can a project manager manually modify?

Show Suggested Answer Hide Answer
Suggested Answer: A

In Adobe Workfront, Planned Dates are the dates that project managers can manually modify. These dates represent the schedule that the project is expected to follow and can be adjusted based on project needs. Estimated and Projected Dates are automatically calculated by the system based on task progress and dependencies, and these cannot be manually modified directly by a project manager. The Projected date is influenced by changes in the actual completion rate of tasks, whereas the Planned Date is the baseline schedule.


Contribute your Thoughts:

0/2000 characters
Ezekiel
1 day ago
I feel B) Estimated could work too. It’s about accuracy.
upvoted 0 times
...
Myong
6 days ago
I’m leaning towards B) Estimated. It can change based on resources.
upvoted 0 times
...
Alison
12 days ago
I agree, A) Planned is the right choice. It's flexible.
upvoted 0 times
...
Rolande
17 days ago
C) Projected is not editable, just so you know!
upvoted 0 times
...
Darrin
22 days ago
Wait, can you really modify A) Planned? That seems off.
upvoted 0 times
...
Dallas
27 days ago
Definitely A) Planned, no doubt about it!
upvoted 0 times
...
Shala
1 month ago
I thought it was B) Estimated.
upvoted 0 times
...
Fernanda
1 month ago
A) Planned is the one you can change manually.
upvoted 0 times
...
Coral
1 month ago
B) Estimated, of course! Isn't that what project managers do all the time, adjust those pesky estimates?
upvoted 0 times
...
Dawne
2 months ago
A) Planned is the obvious choice here. Why wouldn't the project manager be able to modify the planned dates?
upvoted 0 times
...
Krissy
2 months ago
C) Projected seems like the right answer. The project manager should be able to adjust the future projections as the project progresses.
upvoted 0 times
...
Essie
2 months ago
I think the answer is B) Estimated. That's the only one that makes sense for a project manager to manually modify.
upvoted 0 times
...
Micheline
2 months ago
I'm a little confused by the different date types mentioned. I'll have to review my notes on project management to make sure I understand the differences between them.
upvoted 0 times
...
Deonna
2 months ago
I think it's A) Planned. Makes sense to adjust plans.
upvoted 0 times
...
Rex
3 months ago
C) Projected seems tricky. Not sure if it’s adjustable.
upvoted 0 times
...
Merissa
3 months ago
A) Planned is definitely the most logical. We need to adapt!
upvoted 0 times
...
Adela
3 months ago
I've got this! The project manager can manually modify the Estimated date type on tasks. I'm confident that's the right answer.
upvoted 0 times
...
Lisbeth
3 months ago
Okay, let me see. I know the project manager can modify some of the date types, but I'm not positive which ones. I'll have to read the question again and think it through.
upvoted 0 times
...
Kaitlyn
4 months ago
Hmm, I'm not totally sure about this. I'll have to think it through carefully and consider the different date types listed.
upvoted 0 times
...
Isidra
4 months ago
I think I know the answer to this one. The project manager can manually modify the Planned date type on tasks.
upvoted 0 times
Mel
2 months ago
I agree, the Planned date is definitely the one they can change.
upvoted 0 times
...
...
Arlette
4 months ago
I remember a practice question that focused on Planned dates, so I’m leaning towards that option.
upvoted 0 times
...
Ollie
4 months ago
I thought Projected dates were the ones we could adjust, but now I'm second-guessing myself.
upvoted 0 times
...
Julian
4 months ago
I feel like we discussed Estimated dates in class, but I can't recall if they can be manually changed.
upvoted 0 times
...
Quiana
5 months ago
I think the answer might be A) Planned, but I'm not entirely sure. I remember something about modifying dates in project management.
upvoted 0 times
...

Save Cancel