Which date type on tasks can a project manager manually modify?
In Adobe Workfront, Planned Dates are the dates that project managers can manually modify. These dates represent the schedule that the project is expected to follow and can be adjusted based on project needs. Estimated and Projected Dates are automatically calculated by the system based on task progress and dependencies, and these cannot be manually modified directly by a project manager. The Projected date is influenced by changes in the actual completion rate of tasks, whereas the Planned Date is the baseline schedule.
Ezekiel
1 day agoMyong
6 days agoAlison
12 days agoRolande
17 days agoDarrin
22 days agoDallas
27 days agoShala
1 month agoFernanda
1 month agoCoral
1 month agoDawne
2 months agoKrissy
2 months agoEssie
2 months agoMicheline
2 months agoDeonna
2 months agoRex
3 months agoMerissa
3 months agoAdela
3 months agoLisbeth
3 months agoKaitlyn
4 months agoIsidra
4 months agoMel
2 months agoArlette
4 months agoOllie
4 months agoJulian
4 months agoQuiana
5 months ago