Which date type on tasks can a project manager manually modify?
In Adobe Workfront, Planned Dates are the dates that project managers can manually modify. These dates represent the schedule that the project is expected to follow and can be adjusted based on project needs. Estimated and Projected Dates are automatically calculated by the system based on task progress and dependencies, and these cannot be manually modified directly by a project manager. The Projected date is influenced by changes in the actual completion rate of tasks, whereas the Planned Date is the baseline schedule.
Ezekiel
7 months agoMyong
7 months agoAlison
7 months agoRolande
7 months agoDarrin
7 months agoDallas
8 months agoShala
8 months agoFernanda
8 months agoCoral
8 months agoDawne
8 months agoKrissy
8 months agoEssie
9 months agoMicheline
9 months agoDeonna
9 months agoRex
9 months agoMerissa
10 months agoAdela
10 months agoLisbeth
10 months agoKaitlyn
10 months agoIsidra
10 months agoBarrett
6 months agoDaryl
6 months agoDevora
6 months agoMel
9 months agoArlette
11 months agoOllie
11 months agoJulian
11 months agoQuiana
11 months ago