Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

Adobe Exam AD0-E903 Topic 3 Question 26 Discussion

Actual exam question for Adobe's AD0-E903 exam
Question #: 26
Topic #: 3
[All AD0-E903 Questions]

Which date type on tasks can a project manager manually modify?

Show Suggested Answer Hide Answer
Suggested Answer: A

In Adobe Workfront, Planned Dates are the dates that project managers can manually modify. These dates represent the schedule that the project is expected to follow and can be adjusted based on project needs. Estimated and Projected Dates are automatically calculated by the system based on task progress and dependencies, and these cannot be manually modified directly by a project manager. The Projected date is influenced by changes in the actual completion rate of tasks, whereas the Planned Date is the baseline schedule.


Contribute your Thoughts:

Kaitlyn
2 days ago
Hmm, I'm not totally sure about this. I'll have to think it through carefully and consider the different date types listed.
upvoted 0 times
...
Isidra
8 days ago
I think I know the answer to this one. The project manager can manually modify the Planned date type on tasks.
upvoted 0 times
...
Arlette
13 days ago
I remember a practice question that focused on Planned dates, so I’m leaning towards that option.
upvoted 0 times
...
Ollie
19 days ago
I thought Projected dates were the ones we could adjust, but now I'm second-guessing myself.
upvoted 0 times
...
Julian
24 days ago
I feel like we discussed Estimated dates in class, but I can't recall if they can be manually changed.
upvoted 0 times
...
Quiana
1 month ago
I think the answer might be A) Planned, but I'm not entirely sure. I remember something about modifying dates in project management.
upvoted 0 times
...

Save Cancel