Adobe Exam AD0-E903 Topic 3 Question 24 Discussion

Actual exam question for Adobe's AD0-E903 exam
Question #: 24
Topic #: 3
[All AD0-E903 Questions]

Executive stakeholders require both current metric reports and a weekly recap on a project.

How can both needs be met?

Show Suggested Answer Hide Answer
Suggested Answer: A

In Workfront, creating a program-specific dashboard allows for the presentation of real-time data to stakeholders. Additionally, automated reports can be set to send out weekly, meeting the requirement for a consistent recap. This automation reduces the manual effort of downloading and sending reports each week.


Contribute your Thoughts:

Bong
2 days ago
A weekly automated report is definitely the way to go. Saves everyone time and ensures the stakeholders get the info they need.