Which date type should an assignee update to change the completion date of a task?

Show Suggested Answer Hide Answer
Suggested Answer: C

In Workfront, to update the planned completion of a task, the assignee should modify the 'Planned Completion Date.' This date is used for scheduling and planning purposes to track when the task is expected to be finished. Changing the 'Planned Completion Date' adjusts the task's projected timeline and allows for a recalculation of project dependencies.


Contribute your Thoughts:

Ty
6 days ago
I agree with Nickolas. Updating the Planned Completion Date is the logical choice here.
upvoted 0 times
...
Nickolas
11 days ago
The correct answer is C) Planned Completion Date. This makes the most sense, as we need to update the expected completion date of the task.
upvoted 0 times
Ona
3 days ago
B) Commit Date
upvoted 0 times
...
Leah
4 days ago
A) Actual Completion Date
upvoted 0 times
...
...
Devorah
18 days ago
I think the assignee should update the Planned Completion Date.
upvoted 0 times
...