Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

Adobe Exam AD0-E903 Topic 3 Question 13 Discussion

Actual exam question for Adobe's AD0-E903 exam
Question #: 13
Topic #: 3
[All AD0-E903 Questions]

A task was originally planned with a 10-day duration and 40 planned hours. The client needs it done in 3 days.

What task setting needs to change to allow 4 users to complete this in less than 3 days?

Show Suggested Answer Hide Answer
Suggested Answer: C, D

Groups in Adobe Workfront serve as organizational entities that can be associated with specific Companies or Projects to manage workflows or permissions more effectively. Additionally, each Group can have a Group Administrator assigned, who is responsible for managing the group's settings, permissions, and workflows. These roles and associations help in structuring how work and permissions are allocated across different teams or departments.


Contribute your Thoughts:

Herman
1 months ago
Wait, is this a trick question? What if we just hire more people to work on it? That's the real answer, right?
upvoted 0 times
Shaniqua
8 days ago
A) Change the Task Duration Type to Effort Driven
upvoted 0 times
...
...
Lashandra
2 months ago
I'm leaning towards A. Making the task Effort Driven would let the project automatically adjust the duration as more resources are added. Seems like the most straightforward solution.
upvoted 0 times
Erick
8 days ago
D) Change the Task Constraint to As Soon As Possible
upvoted 0 times
...
Reena
1 months ago
That makes sense. Effort Driven would definitely help speed things up.
upvoted 0 times
...
Sylvie
1 months ago
A) Change the Task Duration Type to Effort Driven
upvoted 0 times
...
...
Hoa
2 months ago
Ah, I'm not so sure about that. Changing the Task Constraint to As Soon As Possible seems like the best option to me. That would let the project schedule the task to finish in less than 3 days.
upvoted 0 times
Truman
14 days ago
B) Change the Task Duration Type to Calculated Work
upvoted 0 times
...
Vincenza
17 days ago
D) Change the Task Constraint to As Soon As Possible
upvoted 0 times
...
Felicidad
18 days ago
C) Change the Task Constraint to Fixed Dates
upvoted 0 times
...
Renay
1 months ago
B) Change the Task Duration Type to Calculated Work
upvoted 0 times
...
...
Darci
2 months ago
Hmm, I think the answer is B. Changing the Task Duration Type to Calculated Work would allow the project to adjust the duration based on the increased number of resources.
upvoted 0 times
Apolonia
24 days ago
B) Change the Task Duration Type to Calculated Work
upvoted 0 times
...
Michael
28 days ago
A) Change the Task Duration Type to Effort Driven
upvoted 0 times
...
...
Gracia
2 months ago
Changing the Task Duration Type to Effort Driven makes sense, it will allow us to allocate resources more efficiently.
upvoted 0 times
...
Jackie
2 months ago
I agree with Stacey, Effort Driven will help us complete the task in less than 3 days.
upvoted 0 times
...
Stacey
2 months ago
We need to change the Task Duration Type to Effort Driven.
upvoted 0 times
...

Save Cancel