Taking into consideration any applied task constraints, a project manager needs to know the date that a task is likely to be finished based upon the current progress of the task and its predecessors. Which date type should the project manager utilize?
The Projected Date in Adobe Workfront is dynamically calculated based on the progress of the task, any task constraints, and its dependencies. This date provides a more accurate reflection of when a task is likely to be completed, considering the current progress and any updates to predecessor tasks. On the other hand, the Planned Date refers to the originally scheduled completion date, and the Estimated Date is not manually entered but inferred from system calculations.
Cammy
10 months agoDeja
9 months agoJosephine
9 months agoEdelmira
9 months agoMinna
10 months agoRobt
10 months agoYolande
9 months agoYong
9 months agoRebbecca
9 months agoJenelle
10 months agoJacqueline
10 months agoWillie
10 months agoWilda
10 months agoEarnestine
10 months agoCassi
11 months agoEarnestine
9 months agoArthur
10 months agoReita
10 months agoKenneth
10 months agoGianna
11 months agoMinna
11 months ago