Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

Adobe Exam AD0-E903 Topic 2 Question 18 Discussion

Actual exam question for Adobe's AD0-E903 exam
Question #: 18
Topic #: 2
[All AD0-E903 Questions]

Refer to the exhibit.

Identified in red on a Gantt chart, what are the tasks called whose changes may affect the overall timeline of a project?

Show Suggested Answer Hide Answer
Suggested Answer: B

To measure a project's adherence to its original schedule, the most critical elements are Project Baselines, Planned Completion Dates, and Actual Completion Dates. The baseline captures the original planned schedule, while the planned and actual completion dates provide the data to compare the project's progress against the initial schedule. This comparison helps project managers identify any deviations from the original plan and assess the project's performance.


Contribute your Thoughts:

Cary
13 days ago
Wait, there's a Gantt chart involved? I thought this was a cooking exam. No wonder I'm so confused. Where's the recipe for the perfect project timeline soufflé?
upvoted 0 times
...
Svetlana
15 days ago
Critical Path, no doubt. It's like the backbone of the project schedule. Mess with that, and you might as well just start over from scratch. Although, I did hear a rumor that the correct answer is actually 'Unicorns' - you know, those mythical creatures that can bend the laws of time and space.
upvoted 0 times
...
Shantay
29 days ago
Milestones? Really? I thought those were just the fun checkpoints we get to celebrate. Didn't realize they could mess up the whole timeline. Better double-check that one.
upvoted 0 times
Ceola
16 days ago
B) Baselines
upvoted 0 times
...
Mabelle
20 days ago
A) Critical Path
upvoted 0 times
...
...
Bobbye
1 months ago
Baselines, maybe? That's what I was thinking, but now I'm second-guessing myself. Darn these certification exams and their tricky wording!
upvoted 0 times
Alexia
13 days ago
I think it's A) Critical Path.
upvoted 0 times
...
Reed
15 days ago
C) Milestones
upvoted 0 times
...
Beula
26 days ago
B) Baselines
upvoted 0 times
...
Socorro
27 days ago
A) Critical Path
upvoted 0 times
...
...
Callie
2 months ago
I'm not sure, but I think Milestones could also affect the overall timeline of a project.
upvoted 0 times
...
Nidia
2 months ago
Critical Path, of course! Those tasks are the ones that can really make or break the project timeline. You mess with those, and the whole thing comes crashing down like a house of cards.
upvoted 0 times
No, baselines are important for measuring progress but don't impact the overall timeline like the critical path does.
upvoted 0 times
...
Rodrigo
1 days ago
B) Baselines
upvoted 0 times
...
Kirby
16 days ago
Absolutely, the critical path is crucial for keeping the project on track.
upvoted 0 times
...
Thaddeus
29 days ago
A) Critical Path
upvoted 0 times
...
...
Cassi
2 months ago
I agree with Malcom, Critical Path is the correct answer because it determines the shortest possible duration of a project.
upvoted 0 times
...
Malcom
2 months ago
I think the answer is A) Critical Path.
upvoted 0 times
...

Save Cancel