New Year Sale 2026! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

Adobe AD0-E903 Exam - Topic 1 Question 9 Discussion

Actual exam question for Adobe's AD0-E903 exam
Question #: 9
Topic #: 1
[All AD0-E903 Questions]

The last 5 tasks in a project need to happen within 10 days of the end of the project.

Which Task Constraint should the project manager use to configure this timeline without setting specific dates?

Show Suggested Answer Hide Answer
Suggested Answer: C

In Workfront, the 'As Late As Possible' task constraint ensures that tasks are scheduled as close to the project's end date as possible. This is useful when specific start dates are not necessary, but tasks need to happen near the end of the project timeline. This constraint allows for flexibility while still ensuring that the tasks are completed within the required time frame.


Contribute your Thoughts:

0/2000 characters
Loren
3 months ago
Not sure about C, what if tasks get delayed?
upvoted 0 times
...
Makeda
3 months ago
Totally agree with C, it gives more flexibility!
upvoted 0 times
...
Ryann
3 months ago
Wait, why not just set specific dates? Seems risky!
upvoted 0 times
...
Adela
4 months ago
I think A could work too, but C seems better.
upvoted 0 times
...
Anika
4 months ago
C is the right choice here!
upvoted 0 times
...
Bettyann
4 months ago
I’m a bit confused, but I think "As Late As Possible" aligns with keeping the tasks within that 10-day window.
upvoted 0 times
...
Fanny
4 months ago
I practiced a question like this, and I feel like "Must Start On" could be too rigid for this scenario.
upvoted 0 times
...
Taryn
4 months ago
I'm not entirely sure, but "Start No Later Than" sounds familiar. I remember it being used for deadlines.
upvoted 0 times
...
Carman
5 months ago
I think the "As Late As Possible" constraint might be the right choice since it allows flexibility without specific dates.
upvoted 0 times
...
Tiera
5 months ago
This looks straightforward to me. The project manager needs to ensure the last 5 tasks are completed within 10 days of the end, so "As Late As Possible" is the way to go.
upvoted 0 times
...
Remedios
5 months ago
I'm a bit confused on this one. What's the difference between "Start No Later Than" and "As Late As Possible"? I'll need to review those options again.
upvoted 0 times
...
Nieves
5 months ago
Okay, I think I know the answer here. The key is to configure the timeline without setting specific dates, so "As Late As Possible" seems like the right choice.
upvoted 0 times
...
Judy
5 months ago
Hmm, this one seems tricky. I'll need to think through the different task constraint options carefully.
upvoted 0 times
...
Nieves
5 months ago
I'm feeling pretty confident about this one. The "As Late As Possible" constraint will let the project manager schedule those final tasks as close to the end as possible, which is exactly what the question is asking for.
upvoted 0 times
...
Sena
1 year ago
I prefer the Must Start On constraint. It ensures that the tasks start exactly when we need them to.
upvoted 0 times
...
Veronika
1 year ago
Whichever option you choose, I just hope there's no 'last minute' pizza involved. I've had enough of that in my life, thank you very much!
upvoted 0 times
Lynelle
1 year ago
C) As Late As Possible
upvoted 0 times
...
Chaya
1 year ago
B) Must Start On
upvoted 0 times
...
Melina
1 year ago
I agree, last minute pizza is never a good idea.
upvoted 0 times
...
Ashton
1 year ago
C) As Late As Possible
upvoted 0 times
...
Yun
1 year ago
B) Must Start On
upvoted 0 times
...
Gearldine
1 year ago
A) Start No Later Than
upvoted 0 times
...
Michal
1 year ago
A) Start No Later Than
upvoted 0 times
...
...
Valene
1 year ago
I agree with Mila. It gives us flexibility to start the tasks earlier if needed.
upvoted 0 times
...
Mila
1 year ago
I think we should use the Start No Later Than constraint.
upvoted 0 times
...
Hoa
1 year ago
Hmm, I'm going with A) Start No Later Than. Gives a bit of a buffer, you know? Don't want to be scrambling at the end.
upvoted 0 times
Nichelle
1 year ago
C) As Late As Possible could work if there are no dependencies between the tasks.
upvoted 0 times
...
Nelida
1 year ago
I think B) Must Start On might be better to ensure the tasks are completed on time.
upvoted 0 times
...
Nieves
1 year ago
I agree, A) Start No Later Than is a good choice. It allows for some flexibility.
upvoted 0 times
...
...
Andrew
1 year ago
Definitely B) Must Start On. You can't leave these critical tasks to the last minute, you know. Gotta be organized!
upvoted 0 times
Brendan
1 year ago
Using Must Start On will give the team a clear target to work towards in the final days of the project.
upvoted 0 times
...
Reena
1 year ago
I think it's important to have a clear deadline for those final tasks to avoid any last-minute rush.
upvoted 0 times
...
Frederick
1 year ago
Yeah, setting a specific start date for those tasks will help keep everything on track.
upvoted 0 times
...
Paz
1 year ago
I agree, B) Must Start On is the best option to ensure those tasks are completed on time.
upvoted 0 times
...
...
Franklyn
1 year ago
I think the answer should be C) As Late As Possible. That way the project manager can squeeze out the last bit of time before the deadline.
upvoted 0 times
Ines
1 year ago
But wouldn't A) Start No Later Than also work? It ensures we start those tasks early enough to finish on time.
upvoted 0 times
...
Hillary
1 year ago
I agree, C) As Late As Possible would give us the flexibility we need to finish those tasks right before the deadline.
upvoted 0 times
...
...

Save Cancel