Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

Adobe AD0-E903 Exam - Topic 1 Question 36 Discussion

Two team members are assigned to a task that is expected to start this Tuesday based on the predecessor and the task constraint, but the Planned Start Date is showing as this Friday.Why may this be the case?
C) The task duration and planned hours are set to begin on Friday.
A) The primary task owner has time off logged in Workfront.
B) The team needs to review the task before confirming the start date.

Adobe AD0-E903 Exam - Topic 1 Question 36 Discussion

Actual exam question for Adobe's AD0-E903 exam
Question #: 36
Topic #: 1
[All AD0-E903 Questions]

Two team members are assigned to a task that is expected to start this Tuesday based on the predecessor and the task constraint, but the Planned Start Date is showing as this Friday.

Why may this be the case?

Show Suggested Answer Hide Answer
Suggested Answer: C

In Workfront, tasks are governed by several factors such as task duration, planned hours, and predecessors. In this case, the most likely reason for the task starting later than expected is due to the task's duration and planned hours being configured to start on Friday. Even though the predecessor may suggest an earlier start, task settings such as constraints and assigned hours can override the default scheduling. Additionally, task constraints, like 'Fixed Start' or 'Fixed Finish,' can influence when tasks appear on the schedule.


Contribute your Thoughts:

0/2000 characters
Julene
2 days ago
I think it’s more about the team needing to review first.
upvoted 0 times
...
Elfriede
7 days ago
Totally agree, that could definitely delay things.
upvoted 0 times
...
Melodie
12 days ago
A possible time off for the task owner?
upvoted 0 times
...
Katina
17 days ago
I feel like the Planned Start Date might just be a default setting in Workfront. It’s tricky to know without more context!
upvoted 0 times
...
Mona
22 days ago
I’m not entirely sure, but could it be that the task duration is just set incorrectly? That seems like a possibility too.
upvoted 0 times
...
Pete
28 days ago
I think it could also be that the team needs to review the task first. I’ve seen similar questions where reviews delayed the start.
upvoted 0 times
...
Salome
1 month ago
I remember something about task dependencies affecting start dates, so maybe the primary task owner being off could be a factor.
upvoted 0 times
...

Save Cancel