Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

Adobe Exam AD0-E903 Topic 1 Question 27 Discussion

Actual exam question for Adobe's AD0-E903 exam
Question #: 27
Topic #: 1
[All AD0-E903 Questions]

The second task in a project should be completed within 48 hours and needs to begin 5 business days after the first task is completed.

Which task settings should be configured to meet these requirements?

Show Suggested Answer Hide Answer
Suggested Answer: A

In Adobe Workfront, to configure tasks according to the requirement of the second task beginning 5 business days after the first task, you need to set the appropriate 'Duration' and use 'Finish-Start' dependencies. The task's duration is key to determining the time allowed for its completion. The 'Finish-Start' dependency ensures that the second task begins only after the first is finished, and a lag can be set to introduce a delay, such as 5 business days. Setting a 'Finish-Start' dependency with a lag allows for proper scheduling of tasks in sequence without overlapping.


Contribute your Thoughts:

Ben
3 hours ago
I'm not entirely sure about the difference between Finish-Start and Start-Finish dependencies. I'll need to review that before deciding on the best approach.
upvoted 0 times
...
Victor
6 days ago
I'm leaning towards option C. The task Duration should be set to 48 hours, and a Start-Finish predecessor with a 5-day lag seems to match the requirements.
upvoted 0 times
...
Candra
11 days ago
Hmm, I'm a bit confused. The question says the second task needs to be completed within 48 hours, but option A talks about a 2-day duration. I'm not sure if that's the right approach.
upvoted 0 times
...
Janey
17 days ago
This question seems straightforward. I think I'll go with option A - setting the task Duration to 2 days and adding a Finish-Start predecessor with a 5-day lag.
upvoted 0 times
...

Save Cancel