New Year Sale 2026! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

Adobe AD0-E903 Exam - Topic 1 Question 27 Discussion

Actual exam question for Adobe's AD0-E903 exam
Question #: 27
Topic #: 1
[All AD0-E903 Questions]

The second task in a project should be completed within 48 hours and needs to begin 5 business days after the first task is completed.

Which task settings should be configured to meet these requirements?

Show Suggested Answer Hide Answer
Suggested Answer: A

In Adobe Workfront, to configure tasks according to the requirement of the second task beginning 5 business days after the first task, you need to set the appropriate 'Duration' and use 'Finish-Start' dependencies. The task's duration is key to determining the time allowed for its completion. The 'Finish-Start' dependency ensures that the second task begins only after the first is finished, and a lag can be set to introduce a delay, such as 5 business days. Setting a 'Finish-Start' dependency with a lag allows for proper scheduling of tasks in sequence without overlapping.


Contribute your Thoughts:

0/2000 characters
Louann
1 day ago
I think option A is correct. It fits the timeline perfectly.
upvoted 0 times
...
Brittney
6 days ago
Definitely A), that's how you keep things on track!
upvoted 0 times
...
Tiffiny
12 days ago
Wait, can you really have a Start-Finish dependency? Sounds odd!
upvoted 0 times
...
Arlette
17 days ago
C) doesn't fit the timeline at all, that's confusing.
upvoted 0 times
...
Albina
22 days ago
I disagree, B) seems more logical with the planned hours.
upvoted 0 times
...
Lacey
27 days ago
A) is the right choice! 2 days duration and 5 days lag makes sense.
upvoted 0 times
...
Chan
1 month ago
Lag of 5 days? More like lag of 5 years, am I right? *wink wink*
upvoted 0 times
...
Noel
1 month ago
Planned Hours? Pfft, who plans anymore? Just wing it and see what happens!
upvoted 0 times
...
Idella
1 month ago
C'mon, Start-Finish? What is this, amateur hour? Real project managers use Finish-Start, no doubt.
upvoted 0 times
...
Sherell
2 months ago
48 hours? That's like, a whole weekend! I can binge-watch Netflix and still get the task done.
upvoted 0 times
...
Sherita
2 months ago
I feel like the duration should be set to 48 hours since it mentions completing the task within that time frame. But I’m not clear on the dependency type.
upvoted 0 times
...
German
2 months ago
I practiced a similar question where the dependency type was crucial. I think Finish-Start is the right choice here, but I'm not sure about the lag.
upvoted 0 times
...
Rosalind
2 months ago
Option A seems like the way to go. Gotta love those Finish-Start dependencies!
upvoted 0 times
...
Audra
2 months ago
I’m a bit confused about the lag. I thought the lag should be applied to the predecessor, but I can't recall if it should be 5 days or something else.
upvoted 0 times
...
Carlota
3 months ago
Option B seems off. Planned hours don’t match the task duration.
upvoted 0 times
...
Jin
3 months ago
I remember that the duration should reflect the actual time needed, so I think it should be 2 days, not 48 hours.
upvoted 0 times
...
Henriette
3 months ago
Option B looks promising - setting the Planned Hours to 48 hours and adding a Finish-Start predecessor with a 5-day lag to the first task. That way, the second task can start 5 days after the first one is completed.
upvoted 0 times
...
Ben
4 months ago
I'm not entirely sure about the difference between Finish-Start and Start-Finish dependencies. I'll need to review that before deciding on the best approach.
upvoted 0 times
...
Victor
4 months ago
I'm leaning towards option C. The task Duration should be set to 48 hours, and a Start-Finish predecessor with a 5-day lag seems to match the requirements.
upvoted 0 times
...
Candra
4 months ago
Hmm, I'm a bit confused. The question says the second task needs to be completed within 48 hours, but option A talks about a 2-day duration. I'm not sure if that's the right approach.
upvoted 0 times
...
Janey
4 months ago
This question seems straightforward. I think I'll go with option A - setting the task Duration to 2 days and adding a Finish-Start predecessor with a 5-day lag.
upvoted 0 times
Rupert
2 months ago
I agree, option A looks solid.
upvoted 0 times
...
Rikki
3 months ago
Option B is tempting, but it doesn’t align with the 48-hour task duration.
upvoted 0 times
...
...

Save Cancel