New Year Sale 2026! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

AACE International CCP Exam - Topic 5 Question 37 Discussion

Actual exam question for AACE International's CCP exam
Question #: 37
Topic #: 5
[All CCP Questions]

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

Which of the following is least likely to improve a large earthmoving contractor's productivity?

Show Suggested Answer Hide Answer
Suggested Answer: A

Using apprentice operators to save labor costs is the least likely to improve a large earthmoving contractor's productivity. While it may reduce labor costs, apprentice operators are generally less experienced and less efficient than seasoned operators, which could lead to lower productivity and potentially higher costs due to mistakes or slower work. In contrast, options B, C, and D are all strategies that could directly improve productivity by optimizing working conditions or using more efficient equipment. Hence, the correct answer is A. Using apprentice operators to save labor costs.

Top of Form

Bottom of Form


Contribute your Thoughts:

0/2000 characters

Currently there are no comments in this discussion, be the first to comment!


Save Cancel