AACE International AACE-PSP Exam - Topic 4 Question 59 Discussion

Posted by Leatha on Oct 26, 2026 at 06:16 PM

Free float is the

Suggested Answer: B

Free float is a concept in Critical Path Method (CPM) scheduling that refers to the amount of time an activity's early start can be delayed without affecting the early start of any immediately succeeding activities.

Option A refers to total float, which considers early and late dates of an activity.

Option C also points to total float.

Option D does not define free float.

Free float is critical for project planners as it provides flexibility in scheduling without impacting downstream activities.


Get Premium AACE-PSP Questions as Interactive Web-Based Practice Test or PDF Real Exam Format Detailed Explanations Instant Access Get Your Practice Test
2 comments · newest first
MY
Myra 6 hours ago
I remember something about early and late dates, but I'm not sure if that's the same as free float. Could it be A?
WI
Willard 5 days ago
I think free float is related to how much you can delay an activity without affecting the next one, so maybe it's B?