Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

AACE International AACE-PSP Exam - Topic 4 Question 50 Discussion

What day would Activity C complete if the duration of Activity A was reduced by five days?
B) 30
A) 35
C) 45
D) 40

AACE International AACE-PSP Exam - Topic 4 Question 50 Discussion

Actual exam question for AACE International's AACE-PSP exam
Question #: 50
Topic #: 4
[All AACE-PSP Questions]

What day would Activity C complete if the duration of Activity A was reduced by five days?

Show Suggested Answer Hide Answer
Suggested Answer: B

To calculate the completion day for Activity C:

Reduce Activity A's duration by five days.

Recalculate dependent activities' start and finish times using forward pass logic (PSP Study Guide, Subchapter 2.2.4, 'Relationships').

Sum up the adjusted durations to determine the completion day for Activity C.

This aligns with the logic of schedule adjustments and dependencies as outlined in the PSP Study Guide.


Contribute your Thoughts:

0/2000 characters
Domitila
4 days ago
I agree with Alex, 30 seems right.
upvoted 0 times
...
Lorean
9 days ago
But 35 doesn’t account for the reduction.
upvoted 0 times
...
Ilene
15 days ago
I feel like 35 makes sense too.
upvoted 0 times
...
Brinda
20 days ago
If A is shorter, C finishes sooner.
upvoted 0 times
...
Lorean
25 days ago
Why 30?
upvoted 0 times
...
Brinda
1 month ago
I think it could be 30.
upvoted 0 times
...
Sharika
1 month ago
I'm leaning towards 40 days, seems reasonable.
upvoted 0 times
...
Susana
1 month ago
Wait, are we sure about that? Sounds off to me.
upvoted 0 times
...
Tamra
2 months ago
Reducing A by 5 days could really change things!
upvoted 0 times
...
Shelba
2 months ago
Definitely not 45, that's way too long.
upvoted 0 times
...
Chara
2 months ago
I think it would be 30 days.
upvoted 0 times
...
Julian
2 months ago
I feel like I should be able to figure this out, but I can't recall the exact method we used in class. Maybe I should just take a guess based on the options.
upvoted 0 times
...
Desiree
4 months ago
I'm a bit lost on how to calculate the new completion day for Activity C. Does it depend on the dependencies between activities?
upvoted 0 times
...
Marjory
4 months ago
This kind of question seems familiar! I think we practiced a similar one where changing one activity's duration affected the finish date of another.
upvoted 0 times
...
Lura
4 months ago
I remember something about how reducing the duration of one activity can impact the overall schedule, but I'm not sure how that applies here.
upvoted 0 times
...

Save Cancel