AACE International AACE-PSP Exam - Topic 4 Question 50 Discussion

Actual exam question for AACE International's AACE-PSP exam
Question #: 50
Topic #: 4
[All AACE-PSP Questions]

What day would Activity C complete if the duration of Activity A was reduced by five days?

Show Suggested Answer Hide Answer
Suggested Answer: B

To calculate the completion day for Activity C:

Reduce Activity A's duration by five days.

Recalculate dependent activities' start and finish times using forward pass logic (PSP Study Guide, Subchapter 2.2.4, 'Relationships').

Sum up the adjusted durations to determine the completion day for Activity C.

This aligns with the logic of schedule adjustments and dependencies as outlined in the PSP Study Guide.


Contribute your Thoughts:

0/2000 characters
Marjory
20 hours ago
This kind of question seems familiar! I think we practiced a similar one where changing one activity's duration affected the finish date of another.
upvoted 0 times
...
Lura
6 days ago
I remember something about how reducing the duration of one activity can impact the overall schedule, but I'm not sure how that applies here.
upvoted 0 times
...