What day would Activity C complete if the duration of Activity A was reduced by five days?
To calculate the completion day for Activity C:
Reduce Activity A's duration by five days.
Recalculate dependent activities' start and finish times using forward pass logic (PSP Study Guide, Subchapter 2.2.4, 'Relationships').
Sum up the adjusted durations to determine the completion day for Activity C.
This aligns with the logic of schedule adjustments and dependencies as outlined in the PSP Study Guide.